Press ReleaseSource: Minefinders Corporation Ltd.

Minefinders Commences Leaching at the Dolores Mine and Provides Other Updates
Wednesday October 22, 2008 9:54 am ET

VANCOUVER, BRITISH COLUMBIA--(MARKET WIRE)--Oct 22, 2008 -- Minefinders Corporation Ltd. (the "Company")(Toronto:MFL.TO - News)(MFN - News) is pleased to report the commencement of leaching operations at its Dolores gold and silver mine in Chihuahua, Mexico and provide an update on mine operations.

Commencement of Leaching and Dolores Update

"Leaching of the first ore panel has commenced and we anticipate first gold and silver production in the next few weeks" said Mark Bailey, Minefinders' President and CEO. "This is a significant milestone in the commissioning of the Dolores Mine and an exciting time for our shareholders and those who have been instrumental in the effort to bring this deposit from a grassroots discovery to production."

Mining rates at Dolores continue to meet the mine plan and to date more than 13.5 million tonnes of ore and waste have been moved. The three stage crushing rate has reached 15,000 tonnes per day and is expected to increase to the design capacity of 18,000 tonnes per day as minor commissioning issues are addressed by site personnel. There are now over 300 employees and contractors employed full time in the operation with an additional 250 construction contractors completing ancillary works at the site. The majority of the construction contractors should be demobilized by year end.

The processing facilities, mining operations and support facilities including the warehouse, assay lab and new office complex are now fully operational with the maintenance facilities expected to be commissioned by month end. Recent photos of operations at Dolores can be viewed at www.minefinders.com in the Dolores Gallery.

The Company has successfully arranged a second revolving credit facility with Scotia Capital for an additional $10 million, providing additional working capital in this challenging financing environment. Management expects to meet its cash requirements from funds in place or available through non-equity sources until positive cash flow commences, anticipated by year end.

Community Relations

The Dolores Mine continues to be fully supported by a majority of the local community and ejidatarios, as well as by other community representatives. The state and federal governments have continued to enforce the Company's right to safe access to the mine following intermittent blockades and threats of violence conducted earlier this summer by a small protest group.

Mine management has an ongoing dialogue with the local Ejido and community leaders and maintains an open door policy for government officials and interested parties to visit the mine and see firsthand the Company's commitment to the local communities and environmentally responsible operations.

As previously disclosed, the Company negotiated a comprehensive agreement with the Ejido in 2006 for the development and long-term operation of the mine. In connection with that agreement and in addition to compensation payments, the Company constructed a new village and infrastructure for the local community. The new Dolores village includes electrical, water and sanitation services not previously available to the local population. In addition, the Company constructed public facilities including a new primary school for local children, a modern medical facility with onsite medical professionals, a church and community center, as well as town offices.

About Minefinders

Minefinders is a precious metals mining and exploration company. The Company is in the final stages of commissioning the multi-million ounce Dolores gold and silver mine in Mexico. The mine is expected to have a more than 15-year life as an open pit mine with additional potential as a high-grade underground mine in the future. The Company continues its exploration efforts on several other prospective projects in Mexico to build a quality pipeline of precious metals projects for future growth.

The Dolores open pit mine currently has 99.3 million tonnes of proven and probable reserves containing 2.44 million ounces gold and 126.6 million ounces of silver. Additional resources being considered for underground development occur at depth below the designed pit bottom and in several peripheral structures.

 

Proven and Probable Reserves

NI 43-101 technical report dated March 25, 2008 is available on SEDAR

----------------------------------------------------------------------------
Reserves       Tonnes  Gold       Gold Silver      Silver   AuEq       AuEq
 (1)(2)                (gpt)       (Oz)  (gpt)        (Oz)  (gpt)       (Oz)
                                                              (3)        (3)
----------------------------------------------------------------------------
Proven     56,629,000  0.80  1,453,946  40.32  73,415,147   1.47  2,677,532
----------------------------------------------------------------------------
Probable   42,675,000  0.72    989,713  38.80  53,229,746   1.37  1,876,875
----------------------------------------------------------------------------
Proven &
 Probable  99,305,000  0.77  2,443,659  39.67 126,644,893   1.43  4,554,407
----------------------------------------------------------------------------

(1) Proven and probable reserves have been estimated as of December 31, 2007
    in accordance with definitions adopted by the Canadian Institute of
    Mining, Metallurgy and Petroleum on November 14, 2004. Gustavson has
    prepared and audited these estimates. William J. Crowl of Gustavson is
    the "Qualified Person" as defined in NI 43-101 for this mineral reserve
    statement. Some numbers may not sum due to rounding.
(2) Using $600 per ounce gold; $10.00 per ounce silver.
(3) Gold equivalent ounces ("AuEq") are based on a 60:1 silver to gold
    ratio, without regard to metallurgical recoveries.

Measured and Indicated Resources and Inferred Resources

NI 43-101 technical report dated July 26, 2007 is available on SEDAR

----------------------------------------------------------------------------
Resources       Tonnes  Gold      Gold Silver      Silver   AuEq       AuEq
 (4)(5)                 (gpt)      (Oz)  (gpt)        (Oz)  (gpt)       (Oz)
                                                              (6)        (6)
----------------------------------------------------------------------------
Measured    54,092,000 0.980 1,705,000   46.5  80,788,000  1.754  3,051,000
----------------------------------------------------------------------------
Indicated   52,200,000 0.853 1,432,000   40.5  67,954,000  1.528  2,565,000
----------------------------------------------------------------------------
Measured +
 indicated 106,292,000 0.918 3,137,000   43.5 148,743,000  1.643  5,616,000
----------------------------------------------------------------------------
Inferred    30,350,000 0.677   661,000   28.2  27,517,000  1.147  1,120,000
----------------------------------------------------------------------------

(4) Measured and indicated resources and inferred resources estimates were
    prepared by employees of the Company under the supervision of Mark H.
    Bailey, P. Geol., President and Chief Executive Officer, and audited by
    CAM. Some numbers may not sum due to rounding.
(5) 0.4 gpt AuEq cutoff; cutoff based on gpt AuEq at 75:1 silver to gold
    ratio, having regard to metallurgical recoveries.
(6) Based on updated 60:1 silver to gold ratio, without regard to
    metallurgical recoveries.

Qualified Person

Mark Bailey MSc., P.Geo., is the "qualified person" with overall responsibility for the Dolores Project and is responsible for the contents of this news release.

MINEFINDERS CORPORATION LTD.

Mark H. Bailey, President and Chief Executive Officer

Safe Harbor Statement under the United States Private Securities Litigation Act of 1995: Statements in this release that are forward-looking and other statements that are based on the estimates, projections and expectations of management are subject to various risks and uncertainties concerning the specific factors identified above and in the Company's periodic filings with the regulatory authorities in Canada and the United States. Such statements represent management's best judgment as of the date hereof based on information currently available. The Company does not intend to update this information and disclaims any legal liability to the contrary.

Cautionary Note to U.S. Investors: The SEC permits mining companies to disclose only those mineral deposits that can be extracted or produced economically in their filings with the SEC. This news release uses the term "inferred resource" that the SEC guidelines prohibit from inclusion in filings with the SEC.


Contact:
     Contacts:
     Investor contact:
     Minefinders Corporation Ltd.
     Mike Wills
     (604) 687-6263
     Email: mike@minefinders.com
     Website: http://www.minefinders.com
      

Source: Minefinders Corporation Ltd.


Mail to Friend Email Story
Alerts Set News Alert
Printer
Version  Print Story 


Copyright © 2009 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
Copyright © 2009 Marketwire. All rights reserved. All the news releases provided by Marketwire are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.