Press ReleaseSource: Minefinders Corporation Ltd.

Minefinders Subsidiary Commences Binding Arbitration Seeking US$10 Million in Damages From Ausenco
Friday May 23, 1:08 pm ET

VANCOUVER, BRITISH COLUMBIA--(MARKET WIRE)--May 23, 2008 -- Minefinders Corporation Ltd. (the "Company") (Toronto:MFL.TO - News)(AMEX:MFN - News), a precious metals mining and exploration company, announced today that a subsidiary company has commenced a binding arbitration process seeking approximately US$10 million in damages from Ausenco International PTY of Brisbane, Australia and a related company, Ausenco Americas LLC.

The binding arbitration was launched on May 22, 2008 by Minefinders' subsidiary, Compania Minera Dolores S.A. de CV. ("CMD"), before the International Centre for Dispute Resolution of the American Arbitration Association. In addition to the damages, CMD seeks to recover the costs of the arbitration and its legal fees.

Separately, CMD has assumed responsibility for the final stages of commissioning the multi-million ounce Dolores gold and silver mine in Mexico. Minefinders continues to expect the mine will commence commercial production in mid-2008, based on the updated reserves and economics study disclosed on February 14, 2008. Minefinders believes it has adequate funds in place and available from its revolving credit line to meet its cash needs for the commissioning of the Dolores Mine until the mine reaches full commercial production.

The claim for damages relates to breaches by Ausenco of contracts between CMD and the Ausenco companies, under which Ausenco Americas was to provide engineering and design services for the Dolores mine and Ausenco International was to act as construction manager. In the arbitration Minefinders alleges that the Ausenco companies were responsible for a number of engineering, design and construction problems and delays that increased the cost of developing the Dolores mine compared with expectations prior to the February 14, 2008 study. A portion of this additional cost will be recouped should Minefinders be successful in the arbitration.

Minefinders is aware that Ausenco International filed a writ of summons in Supreme Court of British Columbia on May 9, 2008, against Minefinders and CMD for allegedly not paying US$1.9 million under the construction management agreement. The writ of summons has not been served, and all disputes under the construction management agreement and the engineering services agreement between the parties must be decided by binding arbitration. CMD has demanded that the writ against CMD be withdrawn based upon the mandatory arbitration clause and as against Minefinders because Minefinders is not a party to any of the relevant agreements. CMD intends to vigorously defend against any such claims by Ausenco International or Ausenco Americas.

Qualified Person

Mark Bailey MSc., P.Geo., is the "qualified person" with overall responsibility for the Dolores Project and is responsible for the contents of this news release.

About Minefinders

Minefinders is a precious metals mining and exploration company. The Company is in the final stages of commissioning the multi-million ounce Dolores gold and silver mine in Mexico. Construction at Dolores is substantially complete. Mining within the pit began last fall and, to date, more than 7.3 million tonnes of material has been moved and 700,000 tonnes of development ore stockpiled. Ore is now being crushed and placed on the leach pad with the recently commissioned conveying and stacking system. The mine is expected to have a 15-year life as an open pit mine with additional potential as a high-grade underground mine in the future. The Company continues its exploration efforts on several other prospective projects in Mexico to build a quality pipeline of precious metals projects for future growth.

MINEFINDERS CORPORATION LTD.

Mark H. Bailey, President and Chief Executive Officer

Safe Harbor Statement under the United States Private Securities Litigation Act of 1995: Statements in this release that are forward-looking, including statements relating to the timing of the commencement and completion of the construction of, and the commencement of production from, the Dolores mine, the anticipated costs related to the Dolores mine, the adequacy of the capital and anticipated expenditures for working capital and exploration, and other statements that are based on the estimates, projections and expectations of management are subject to various risks and uncertainties concerning the specific factors identified above and in the Company's periodic filings with the regulatory authorities in Canada and the United States. Such information contained herein represents management's best judgment as of the date hereof based on information currently available. The Company does not intend to update this information and disclaims any legal liability to the contrary.


Contact:
     Contacts:
     Minefinders Corporation Ltd.
     Mike Wills
     Investor Contact
     (604) 687-6263
     (604) 687-6267 (FAX)
     Email: mike@minefinders.com
     Website: http://www.minefinders.com
      

Source: Minefinders Corporation Ltd.


Mail to Friend Email Story
Alerts Set News Alert
Printer
Version  Print Story 


Copyright © 2008 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
Copyright © 2008 Marketwire. All rights reserved. All the news releases provided by Marketwire are copyrighted. Any forms of copying other than an individual user's personal reference without express written permission is prohibited. Further distribution of these materials is strictly forbidden, including but not limited to, posting, emailing, faxing, archiving in a public database, redistributing via a computer network or in a printed form.