Bonaventure Update on Winter Drilling at K9 VANCOUVER, BRITISH COLUMBIA--(MARKET WIRE)--Apr 1, 2008 -- BONAVENTURE ENTERPRISES INC. (CDNX:BVT.V - News)(Frankfurt:YQG.F - News)
is pleased to provide an update on its previously announced
start of the 2008 drilling program at the Company's K9 Uranium
Property ("K9") in the James Bay Mining District.
Up to 14 near surface uranium targets from the K9 uranium corridor are being drilled using two core drill rigs. To date, a total of 1,623 m of NQ-sized coring has been completed in 8 holes, with 2 holes in progress, centered on Target 8 that encompasses Targets 4 thru 9, part of the original 1,200 m by 1,000 m "A" Zone. Drill core descriptions and sampling of the first 8 holes has been completed, as well as down hole scintillometer surveying. The exploration team has been able to recognize key uranium-bearing lithologies, alterations and structures, as observed at surface in 2007. The average 150 m long drill holes show continuous radioactive zones with spiky down hole radiometric signatures which have been correlated with uranium-bearing radiometric highs recorded in up-dip surface outcrops, thus adding to the three-dimensional picture of the K9 uranium corridor. However, U3O8 assay results are still pending and will be issued as they become available. The first 38 proposed drill holes for approximately 6,000 m will test all of the bedrock anomalous areas of Targets 1 to 14 (refer to the appended table for a listing of the diamond drill holes) along the 7 km K9 uranium corridor. Additional drilling is planned to delineate zones of higher grade uranium and mineral resource definition. The salient features of the K9 Uranium Corridor (refer to previous Bonaventure news releases dated October 1, October 16 and November 12, 2007; and February 20 and March 4, 2008) are: - A primary (surface) 7 km long uranium anomaly averaging 675 m in width; - Equivalent uranium assays (or eU3O8) from a total of 522 readings in the corridor averaged 0.05% eU3O8; - Equivalent uranium assays from 94 individual bedrock surface samples taken from the corridor averaged 0.12% eU3O8; - 91 of 94 bedrock samples chemically assayed averaged 0.14% U3O8 (2.80 lbs/ton U3O8); and - Equivalent uranium assays from 88 readings of surface outcrops of the Target 8 sector currently being drilled averaged 0.08% eU3O8; whereas chemical assays from the 26 bedrock samples averaged 0.21% U3O8. Exploration to date on K9 indicates a significant two-dimensional uranium system covering 5.25 km2 in the near-vertical dipping lithologies. The uranium system is open laterally and at depth. K9 is being explored for Rossing-type uranium, a very large low grade, essentially mono-mineralic uranium deposit (with associated thorium) that is mined as a large-scale open-pit operation in Namibia. The principal exploration target is multiple uranium-bearing pegmatites, upwards of 30 m in thickness, in gneisses. Mining volume is usually created by the emplacement of many pegmatites in close proximity. This type of mineralization generally shows kilometric airborne radiometric anomalies for uranium similar to what is found at K9. Uranium levels in the pegmatites are 25 times background between 0.0075% (0.15 lbs/ton) to 0.01% (0.20 lbs/ton) U3O8. The Rossing Deposit average grade is around 0.032% (0.64 lbs/ton) U3O8, or approximately 100 times background values. At current uranium prices, it is conceivable that the Rossing Deposit can be economically mined at a grade as low as 0.008% (0.16 lbs/ton) U3O8 or approximately 25 times background values. The information contained in this release was prepared and revised by Mr. Jean Lafleur, P. Geo., President & CEO of Bonaventure Enterprises Inc., and a Qualified Person under National Instrument 43-101 standards. About Bonaventure Enterprises Bonaventure Enterprises Inc. is a Canadian based resource and exploration company traded publicly under the symbol BVT on the TSX Venture Exchange and YQG on the Frankfurt Stock Exchange. In Nevada, the Company holds 100% of the mineral exploration properties including Goldfield, Cottonwood, Jet and Northern Lights. The Company also has an option agreement with U.S. Gold Corporation (Toronto:UXG.TO - News) to acquire up to 60% interest in the New Pass (Eureka) and Squaw Creek (Carlin Trend) Properties. Bonaventure also has uranium, poly-metallic and diamond assets in the Athabasca Basin, uranium properties in the James Bay and North Shore regions of Quebec. Bonaventure is focused on the creation of shareholder value and building a first-tier company through the acquisition and development of large projects demonstrating the ability to host World-Class mineral deposits. Please visit the Bonaventure Enterprises website at www.bonaventure.us. ON BEHALF OF THE BOARD Jean Lafleur, P. Geo., President and CEO This news release may contain forward-looking statements reflecting the Company's objectives, estimates, expectations and the impact of acquisitions on the Company's financial performance. By their very nature, these types of statements involve risks and uncertainty. Consequently, reality may differ materially from the Company's projections or expectations.
Diamond drill hole coordinates and statistics from the 2008 campaign.
---------------------------------------------------------------------------
PROPOSED COMPLETED
AZIMUTH/ LENGTH LENGTH TARGET
DDH # EASTING NORTHING DIP (m) (m) SITE
---------------------------------------------------------------------------
K9-01 411703 6060267 205/-60 150 150 8B
---------------------------------------------------------------------------
K9-02 411753 6060358 205/-60 150 150 1
---------------------------------------------------------------------------
K9-03 411808 6060436 205/-60 150 to be drilled 8
---------------------------------------------------------------------------
K9-04 411673 6060170 205/-60 150 146 8B
---------------------------------------------------------------------------
K9-05 411633 6060098 205/-60 150 150 8
---------------------------------------------------------------------------
K9-06 411593 6060016 205/-60 150 150 8A
---------------------------------------------------------------------------
K9-07 411540 6059910 205/-60 150 150 8A
---------------------------------------------------------------------------
K9-08 411659 6059951 205/-60 150 148 5
---------------------------------------------------------------------------
K9-09 411608 6059875 205/-60 150 291(i) 8A
---------------------------------------------------------------------------
K9-10 412100 6060594 205/-60 300 to be drilled 5
---------------------------------------------------------------------------
K9-11 411503 6060285 205/-60 200 to be drilled 8A
---------------------------------------------------------------------------
K9-12 411458 6060197 205/-60 200 87(i) 8A
---------------------------------------------------------------------------
K9-13 411418 6060105 205/-60 200 201 8B
---------------------------------------------------------------------------
K9-14 411122 6060612 205/-60 150 to be drilled 7
---------------------------------------------------------------------------
K9-15 414084 6059462 205/-60 150 to be drilled 5
---------------------------------------------------------------------------
K9-16 414065 6059497 205/-60 150 to be drilled 13
---------------------------------------------------------------------------
K9-17 414143 6059461 205/-60 150 to be drilled 13
---------------------------------------------------------------------------
K9-18 414239 6059420 205/-60 150 to be drilled 13
---------------------------------------------------------------------------
K9-19 413344 6059759 205/-60 150 to be drilled 13
---------------------------------------------------------------------------
K9-20 413346 6059745 270/-60 150 to be drilled 13
---------------------------------------------------------------------------
K9-21 413196 6059804 205/-60 150 to be drilled 12
---------------------------------------------------------------------------
K9-22 412952 6059749 205/-60 150 to be drilled 11
---------------------------------------------------------------------------
K9-23 412673 6060249 240/-60 150 to be drilled 12
---------------------------------------------------------------------------
K9-24 412348 6060225 205/-60 150 to be drilled 11
---------------------------------------------------------------------------
K9-25 411792 6060210 205/-60 150 to be drilled 10
---------------------------------------------------------------------------
K9-26 411902 6060426 205/-60 150 to be drilled 10
---------------------------------------------------------------------------
K9-27 411488 6060468 205/-60 150 to be drilled 8B
---------------------------------------------------------------------------
K9-28 411130 6060165 205/-60 150 to be drilled 8
---------------------------------------------------------------------------
K9-29 410550 6060351 205/-60 150 to be drilled 6
---------------------------------------------------------------------------
K9-30 410639 6060314 205/-60 150 to be drilled 4
---------------------------------------------------------------------------
K9-31 410532 6060761 205/-60 150 to be drilled 2
---------------------------------------------------------------------------
K9-32 410488 6060664 205/-60 150 to be drilled 2
---------------------------------------------------------------------------
K9-33 410439 6060566 205/-60 150 to be drilled 1
---------------------------------------------------------------------------
K9-34 410577 6060857 205/-60 150 to be drilled 1
---------------------------------------------------------------------------
K9-35 410598 6060450 205/-60 150 to be drilled 1
---------------------------------------------------------------------------
K9-36 410091 6060765 205/-60 150 to be drilled 2
---------------------------------------------------------------------------
K9-37 410167 6060885 205/-60 150 to be drilled 2
---------------------------------------------------------------------------
K9-38 409614 6061197 205/-60 150 to be drilled 1
---------------------------------------------------------------------------
TOTAL 6,000 m 1,046 m
---------------------------------------------------------------------------
(i) Drilling in progress
Contact: Contacts:
First Canadian Capital