Form 8-K for PINNACLE WEST CAPITAL CORP


30-Dec-2013

Other Events


Item 8.01 Other Events.

Four Corners and Retail Rate Case Filing with the Arizona Corporation Commission

On December 30, 2013, Arizona Public Service Company ("APS") and Southern California Edison Company ("SCE") closed their previously announced transaction whereby APS agreed to purchase SCE's 48% interest in each of Units 4 and 5 of the Four Corners Power Plant ("Four Corners"). The final purchase price for the interest was approximately $182 million, subject to certain minor post-closing adjustments.

In connection with APS's most recent retail rate case with the Arizona Corporation Commission ("ACC"), the ACC reserved the right to review the prudence of the Four Corners transaction for cost recovery purposes upon the closing of the transaction. On December 30, 2013, APS filed an application to request rate adjustments prior to its next general rate case related to APS's acquisition of SCE's interest in Four Corners. If approved, these would result in an average bill impact to residential customers of approximately 2%. APS cannot predict the outcome of this request.

Concurrently with the closing of the SCE transaction, the ownership of BHP Navajo Coal Company, the coal supplier and operator of the mine that serves Four Corners, was transferred to Navajo Transitional Energy Company, LLC ("NTEC"), a company formed by the Navajo Nation to own the mine and develop other energy projects. Also occurring concurrently, the Four Corners co-owners executed a long term agreement for the supply of coal to Four Corners from July 2016, when the current coal supply agreement expires, through 2031 (the "2016 Coal Supply Agreement"). El Paso Electric Company, a 7% owner in Units 4 and 5 of Four Corners, did not sign the 2016 Coal Supply Agreement. Under the 2016 Coal Supply Agreement, APS has agreed to assume the 7% shortfall obligation. APS has also granted NTEC an option to purchase the 7% interest in the plant within a certain timeframe. The 2016 Coal Supply Agreement contains alternate pricing terms for the 7% shortfall obligations in the event NTEC does not purchase the 7% interest.

As previously disclosed, the Four Corners co-owners were required to elect one of two emissions alternatives to apply to the plant under the Environmental Protection Agency's ("EPA") final regional haze rule by the end of 2013. On December 30, 2013, APS, on behalf of the co-owners, notified EPA that they have chosen the alternative BART compliance strategy requiring the permanent closure of Units 1, 2, and 3 by January 1, 2014 and installation and operation of selective catalytic reduction controls ("SCR") on Units 4 and 5 by July 31, 2018. Based on EPA's final standards, APS's share of SCR costs at Four Corners would be approximately $350 million.


  Add PNW to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for PNW - All Recent SEC Filings
Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.