LNT > SEC Filings for LNT > Form 8-K on 13-Dec-2013All Recent SEC Filings

Show all filings for ALLIANT ENERGY CORP

Form 8-K for ALLIANT ENERGY CORP


13-Dec-2013

Regulation FD Disclosure


Item 7.01 Regulation FD.

On December 16, 2013, representatives of Alliant Energy Corporation and Interstate Power and Light Company (Alliant Energy's Iowa utility) will attend an investor conference. The following regulatory update is being provided in connection with that conference.

Alliant Energy provides update on Marshalltown Generation Station (MGS) activities and transmission

As previously announced, Iowa Utilities Board (IUB) Chair Jacobs, as presiding officer for the MGS administrative hearing, issued the Proposed Decision and Order on November 9, 2013 and Alliant Energy's Iowa utility accepted such order on November 19, 2013. The order provides a cost cap for the project of $920 million, including the facility, transmission costs, owners' costs and AFUDC.

On December 9, 2013 Chair Jacobs issued an Order Clarifying Decision, in response to an intervener's request for clarification, stating that all costs related to the transmission construction and reimbursements, including any potential tax gross up payments, are included in the $920 million cost cap. The clarifying decision also stated the cost cap is not reduced if Alliant Energy's Iowa utility receives reimbursement for MGS transmission costs. However, refunds or reimbursements from other interconnecting generators received by Alliant Energy's Iowa utility for any MGS transmission upgrade costs would be returned to ratepayers in a manner to be determined by the IUB. According to the clarifying decision, all transmission network upgrade costs, including amounts for which Alliant Energy's Iowa utility might be reimbursed, are included in the overall cost cap.

Alliant Energy's Iowa utility expected to fund capital transmission upgrades for MGS based on the July 2013 FERC Attachment FF decision (Docket No. EL12-104-000) and assumed such upgrades in its capital expenditure guidance issued on November 7, 2013. Alliant Energy's Iowa utility has been informally notified that ITC Midwest LLC (ITC-M) intends to pursue an option under the terms of the MISO Generator Interconnection Procedures to self-fund the transmission upgrades associated with MGS. Under this option, Alliant Energy's Iowa utility anticipates a direct assignment facility expense for the network upgrades after the upgrades are placed into service. Alliant Energy's Iowa utility does not believe that the cost cap included in the Proposed Decision and Order would be affected if ITC-M were to ultimately self-fund the transmission upgrade.

The IUB's overall approval of MGS is conditional upon attaining other permitting approvals necessary to construct and operate the MGS. One required approval is IUB approval of construction of the gas pipeline necessary to service the facility. Recently, Alliant Energy's Iowa utility received final approval of the needed gas pipeline construction. Pending all additional regulatory approvals, IPL expects to begin construction on MGS in 2014 and begin operations in 2017.


This Current Report on Form 8-K contains forward-looking statements. These forward-looking statements can be identified as such because the statements include words such as "believe," "expects," "anticipates," "may," "would" or other words of similar import. Similarly, statements that describe future plans or strategies are also forward-looking statements. Such statements are subject to certain risks and uncertainties that could cause actual results to differ materially from those currently anticipated. Actual results could be affected by such factors as: state or federal regulatory actions or local government actions, including inability to obtain all necessary approvals and permits; current or future litigation, regulatory investigations, proceedings, appeals or inquiries that could impede the implementation of IPL's plans; changes in costs of materials, equipment, commodities, fuel or labor; shortages in materials, equipment and qualified labor; changes to the scope or timing of the projects; general contractors or subcontractors not performing as required under their contracts; the inability to agree to contract terms or disputes in contract terms; poor initial cost estimates; work stoppages; adverse weather conditions; adverse interpretation or enforcement of permit conditions; changes in applicable laws or regulations; unforeseen engineering or technology issues; and limited access to capital and other adverse economic conditions. These factors should be considered when evaluating the forward-looking statements and undue reliance should not be placed on such statements. The forward-looking statements included herein are made as of the date hereof and Alliant Energy and Interstate Power and Light Company undertake no obligation to update publicly such statements to reflect subsequent events or circumstances.


  Add LNT to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for LNT - All Recent SEC Filings
Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.