Search the web
Welcome, Guest
[Sign Out, My Account]
EDGAR_Online

Quotes & Info
Enter Symbol(s):
e.g. YHOO, ^DJI
Symbol Lookup | Financial Search
CDZI > SEC Filings for CDZI > Form 10-Q on 9-May-2013All Recent SEC Filings

Show all filings for CADIZ INC | Request a Trial to NEW EDGAR Online Pro

Form 10-Q for CADIZ INC


9-May-2013

Quarterly Report

2003 Management Equity Incentive Plan

In December 2003, concurrently with the completion of the Company's then current financing arrangements with ING, the Company's board of directors authorized the adoption of a Management Equity Incentive Plan. As of March 31, 2013, a total of 315,000 common stock options remain outstanding under this plan.

Back to Index Outside Director Compensation Plan

The Cadiz Inc. Outside Director Compensation Plan was approved by Cadiz stockholders in November 2006. Under the plan, each outside director receives $30,000 of cash compensation and receives a deferred stock award consisting of shares of the Company's common stock with a value equal to $20,000 on June 30 of each year. The award accrues on a quarterly basis, with $7,500 of cash compensation and $5,000 of stock earned for each fiscal quarter in which a director serves. The deferred stock award vests automatically on the January 31st which first follows the award date.

2007 Management Equity Incentive Plan

The 2007 Management Equity Incentive Plan was approved by stockholders at the 2007 Annual Meeting. As of March 31, 2013, a total of 10,000 common stock options remain outstanding under this plan.

2009 Equity Incentive Plan

The 2009 Equity Incentive Plan was approved by stockholders at the 2009 Annual Meeting. The plan provides for the grant and issuance of up to 850,000 shares and options to the Company's employees and consultants. The plan became effective when the Company filed a registration statement on Form S-8 on December 18, 2009. All options issued under the 2009 Equity Incentive Plan have a ten year term with vesting periods ranging from issuance date to 24 months. To date, 537,500 common stock purchase options have been issued under this plan and all remained outstanding as of March 31, 2013.

All options that have been issued under the above plans have been issued to officers, employees and consultants of the Company. In total, options to purchase 862,500 shares were unexercised and outstanding on March 31, 2013, under the three equity incentive plans.

The Company recognized stock option related compensation costs of $41,000 and $134,000 in the three months ended March 31, 2013 and 2012, respectively. On March 31, 2013, there was $4,000 of unamortized compensation expense relating to option awards. This unamortized compensation expense is expected to be recognized through December 2013. No options were exercised during the three months ended March 31, 2013.

Stock Awards to Directors, Officers, and Consultants

The Company has granted stock awards pursuant to its 2007 Management Equity Incentive Plan, 2009 Equity Incentive Plan and Outside Director Compensation Plan.

240,000 shares were issued under the 2007 Management Equity Incentive Plan. A 150,000 share award was issued that vested in three equal installments on January 1, 2008, January 1, 2009, and January 1, 2010. The remaining 90,000 shares were issued as shares that vested in May 2009 consistent with the terms of the agreements pursuant to which those executives provide services to the Company.

Back to Index Of the total 850,000 shares reserved under the 2009 Equity Incentive Plan, a grant of 115,000 restricted shares of common stock became effective on January 14, 2010, and a grant of 140,000 restricted shares of common stock became effective on January 10, 2011, consistent with the terms of the agreements pursuant to which those executives provide services to the Company and which contemplate that such executives will participate in the Company's long-term incentive plans. The recipients of these restricted shares have a contractual agreement not to sell any of these shares for a period of three years following the effective date. Of the remaining 595,000 shares reserved under the 2009 Equity Incentive Plan, 22,782 shares of common stock were awarded to directors, 537,500 were issued as options as described above and 34,718 are available for future distribution as of March 31, 2013

Under the Outside Director Compensation Plan, 72,782 shares have been awarded for the plan years ended June 30, 2003, through June 30, 2012. Of the 72,782 shares awarded, 13,795 shares awarded for services during the plan year ended June 30, 2012, became effective on that date and vested on January 31, 2013.

The Company recognized stock based compensation costs related to stock based awards of $25,000 for each of the three months ended March 31, 2013 and 2012.

Stock Purchase Warrants Issued to Non-Employees

The Company accounts for equity securities issued to non-employees in accordance with the provisions of ASC 718 and ASC 505.

On November 30, 2011, the Company raised $6 million with a private placement of 666,667 shares of Common Stock at a price of $9 per share. For every three
(3) shares of Common Stock issued, the Company issued one (1) Common Stock purchase warrant entitling the holder to purchase, commencing 90 days from the date of the issuance and prior to December 8, 2014, one (1) share of Common Stock at an exercise price of $13 per share.

On October 30, 2012, the Company increased the capacity of its then existing Term Loan facility with an additional $5 million facility. Concurrently with the funding of the facility, the Company issued warrants to the lenders to purchase an aggregate of 250,000 shares of its common stock. These warrants have an exercise price of $10 per share and must be exercised not later than two years from the date of issuance.

As of March 31, 2013, 472,222 warrants remain outstanding.

NOTE 6 - INCOME TAXES

As of March 31, 2013, the Company had net operating loss ("NOL") carryforwards of approximately $188 million for federal income tax purposes and $98 million for California state income tax purposes. Such carryforwards expire in varying amounts through the year 2033. Use of the carryforward amounts is subject to an annual limitation as a result of ownership changes.

Back to Index As of March 31, 2013, the Company possessed unrecognized tax benefits totaling approximately $2.8 million. None of these, if recognized, would affect the Company's effective tax rate because the Company has recorded a full valuation allowance against these assets.

The Company's tax years 2009 through 2012 remain subject to examination by the Internal Revenue Service, and tax years 2008 through 2012 remain subject to examination by California tax jurisdictions. In addition, the Company's loss carryforward amounts are generally subject to examination and adjustment for a period of three years for federal tax purposes and four years for California purposes, beginning when such carryovers are utilized to reduce taxes in a future tax year.

Because it is more likely than not that the Company will not realize its net deferred tax assets, it has recorded a full valuation allowance against these assets. Accordingly, no deferred tax asset has been reflected in the accompanying consolidated balance sheets.

NOTE 7 - NET LOSS PER COMMON SHARE

Basic earnings per share ("EPS") is computed by dividing the net loss by the weighted-average common shares outstanding. Options, deferred stock units, warrants and the zero coupon term loan convertible into or exercisable for certain shares of the Company's common stock were not considered in the computation of diluted EPS because their inclusion would have been antidilutive. Had these instruments been included, the fully diluted weighted average shares outstanding would have increased by approximately 3,272,000 and 2,931,000 for the three months ended March 31, 2013 and 2012, respectively.

NOTE 8 - CONTINGENCIES

In California, third parties have the ability to file litigation challenging the approval of a project. As a result, the Company is and expects to continue to be party to various legal proceedings arising in the general course of its business, including, in particular, the development of the Water Project.

The Company is currently named as a real party in interest in eight (8) lawsuits related to the Water Project approvals granted last year by the Santa Margarita Water District and County of San Bernardino in accordance with the California Environmental Quality Act ("CEQA"). The eight lawsuits have been brought by four plaintiffs and have been coordinated in Orange County Superior Court. The cases seek various forms of relief, but are primarily focused on causing a reconsideration of the environmental documents and limitation of the Project approvals. The cases are expected to proceed to administrative trial later this year. The Company cannot predict the outcome of any of the proceedings. In the opinion of management, the ultimate outcome of each proceeding, individually and in the aggregate, will not have a material adverse impact on the Company's financial position, results of operations or cash flows.

There are no other material legal proceedings pending to which the Company is a party or of which any of the Company's property is the subject.

Back to Index ITEM 2. Management's Discussion and Analysis of Financial Condition and Results of Operations

In connection with the "safe harbor" provisions of the Private Securities Litigation Reform Act of 1995, the following discussion contains trend analysis and other forward-looking statements. Forward-looking statements can be identified by the use of words such as "intends", "anticipates", "believes", "estimates", "projects", "forecasts", "expects", "plans" and "proposes". Although we believe that the expectations reflected in these forward-looking statements are based on reasonable assumptions, there are a number of risks and uncertainties that could cause actual results to differ materially from these forward-looking statements. These include, among others, our ability to maximize value from our Cadiz, California land and water resources; and our ability to obtain new financings as needed to meet our ongoing working capital needs. See additional discussion under the heading "Risk Factors" in Item 1A of our Annual Report on Form 10-K for the year ended December 31, 2012.

Overview

We are a land and water resource development company with 45,000 acres of land in three separate areas of eastern San Bernardino County, California. Virtually all of this land is underlain by high-quality, naturally recharging groundwater resources, and is situated in proximity to the Colorado River and the Colorado River Aqueduct ("CRA"), the major source of imported water for Southern California. Our main objective is to realize the highest and best use of these land and water resources in an environmentally responsible way.

For more than 20 years, we have maintained an agricultural development at our 34,000-acre property in the Cadiz Valley, relying upon groundwater from the underlying aquifer system for irrigation. In 1993, we secured permits to develop agriculture on up to 9,600 acres of the Cadiz Valley property and withdraw more than one million acre-feet of groundwater from the underlying aquifer system. Since that time, we have maintained various levels of agriculture at the property and this operation has provided our principal source of revenue.

In addition to our sustainable agricultural operations, we believe that the long-term value of our land assets can best be derived through the development of a combination of water supply and storage projects at our properties. The primary factor driving the value of such projects is continuing pressure on water supplies throughout California, including environmental restrictions and regulatory shortages on each of the State's three main water sources: the State Water Project, the Colorado River and the Los Angeles Aqueduct. Southern California's water providers rely on these imported sources for a majority of their water supplies, but deliveries from all three systems have been below capacity over the last several years. Availability of supplies in California also differs greatly from year to year due to natural hydrological variability. For example, State Water Project deliveries are presently limited to just 35% of capacity for 2013 due to ongoing environmental restrictions and below average precipitation. Southern California water providers are seeking new, reliable supply solutions to address anticipated limitations of traditional water supplies and to plan for long-term water needs but cost-effective alternatives and solutions are limited.

Back to Index At present, our water development efforts are primarily focused on the Cadiz Valley Water Conservation, Recovery and Storage Project ("Water Project" or "Project"), which will capture and conserve millions of acre-feet of native groundwater currently being lost to evaporation from the aquifer system beneath our Cadiz Valley property and deliver it to water providers throughout Southern California (see "Water Resource Development"). We believe that the ultimate implementation of this Water Project will create the primary source of our future cash flow and, accordingly, our working capital requirements relate largely to the development activities associated with this Water Project.

We also continue to explore additional uses of our land and water resource assets, including additional agricultural opportunities, renewable energy power generation opportunities, and the development of a land conservation bank on our properties outside the Water Project area.

In addition to these development efforts, we will also pursue strategic investments in complementary business or infrastructure to meet our objectives. We cannot predict with certainty when or if these objectives will be realized.

Water Resource Development

The Water Project is designed to capture and conserve billions of gallons of renewable native groundwater currently being lost annually to evaporation from the aquifer system underlying our Cadiz/Fenner Property, and provide a new, reliable water supply in Southern California. By implementing established groundwater management practices, the Water Project will create a sustainable water supply for Project participants without adversely impacting the aquifer system or the desert environment. The total quantity of groundwater to be recovered and conveyed to Project participants will not exceed a long-term annual average of 50,000 acre-feet per year for 50 years. The Project also offers participants the ability to carry-over their annual supply and store it in the groundwater basin from year to year. A second phase of the Project, Phase II, will offer approximately one million acre-feet of storage capacity that can be used to store imported water supplies at the Water Project area.

Facilities required for Phase I of the Project primarily include, among other things:

High yield wells designed to efficiently recover available native groundwater from beneath the Water Project area;

A 43-mile water conveyance pipeline to deliver water from the well field to the CRA; and

An energy source to provide power to the well-field, pipeline and pumping plant.

If an imported water storage component of the project is ultimately implemented in Phase II, the following additional facilities would be required, among other things:

A pumping plant to pump water through the conveyance pipeline from the CRA to the Project well-field; and

Spreading basins, which are shallow settling ponds that will be configured to efficiently percolate water from the ground surface down to the water table using subsurface storage capacity for the storage of water.

Back to Index In general, several elements are needed to implement such a project: (1) a water conveyance pipeline right-of-way from the Water Project area to a delivery system; (2) storage and supply agreements with one or more public water agencies or private water utilities; (3) environmental/regulatory permits; and (4) construction and working capital financing. As described below, the first three elements have been progressed on a concurrent basis. The fourth is dependent on actions arising from the completion of the first three.

(1) A Water Conveyance Pipeline Right-of-Way from the Water Project Area to a Delivery System

In September 2008, we secured a right-of-way for the Water Project's water conveyance pipeline by entering into a lease agreement with the Arizona & California Railroad Company ("ARZC"). The agreement allows for the use of a portion of the railroad's right-of-way to construct and operate a water conveyance pipeline for a period up to 99 years. The pipeline would be used to convey water between our Cadiz Valley property and the CRA in Rice, California. The ARZC is also a Project participant and would receive water from the Project to serve a variety of railroad purposes, including fire suppression and other safety and maintenance uses. Pursuant to the agreement, we made a payment in the amount of $3.3 million on March 6, 2013, to commence the construction and operation term of the agreement.

We are also exploring the potential to utilize an unused natural gas pipeline (as described in "Existing Pipeline Asset" below) that exists in the Project area, to which we hold an ownership right, as a means to access additional distribution systems. Initial feasibility studies indicate that this pipeline could be used as a component of the Project to distribute water to Project participants or import water for storage at the Project area in Phase II. The potential use of this pipeline by the Project was preliminarily analyzed as part of the Project's Environmental Impact Report ("EIR").

(2) Storage and Supply Agreements with One or More Public Water Agencies or Private Water Utilities

In 2010 and 2011, we entered into option and environmental cost sharing agreements with six water providers: Santa Margarita Water District ("SMWD"), Golden State Water Company (a wholly-owned subsidiary of American States Water
[NYSE: AWR]), Three Valleys Municipal Water District, Suburban Water Systems (a wholly owned subsidiary of SouthWest Water Company), Jurupa Community Services District and California Water Service Company, the third largest investor-owned American water utility. The six water providers serve more than one million customers in cities throughout California's San Bernardino, Riverside, Los Angeles, Orange and Ventura Counties.

Under the terms of the agreements with the six water providers, upon completion of the Water Project's California Environmental Quality Act ("CEQA") review and certification of the Final EIR, which occurred on July 31, 2012, each agency has the right to acquire an annual supply of 5,000 acre-feet of water at a pre-determined formula competitive with their incremental cost of new water. In addition, the agencies have options to acquire storage rights in the Water Project to allow them to manage their supplies to complement their other water resources.

Back to Index Following CEQA certification, SMWD was the first participant to adopt resolutions approving a Water Purchase and Sale Agreement for 5,000 acre-fee of water. The structure of the SMWD purchase agreement calls for an annually adjusted water supply payment of up to $500/AF including identified income streams, plus its pro rata portion of the capital recovery charge and operating and maintenance costs. The capital recovery charge is calculated by amortizing the total capital investment by the Company over a 30-year term.

Approximately 80% of the water to be conserved annually by the Project is now either under a Water Purchase and Sale Agreement or remains under option. We are currently working with other participating agencies to convert their option agreements to definitive economic agreements.

We are also in discussions with additional water providers interested in acquiring rights to the remaining available Project supplies, as well as with third parties regarding the imported storage aspect of this Project.

(3) Environmental Permits

In order to properly develop and quantify the sustainability of the Water Project, and prior to initiating the formal permitting process for the Water Project, we commissioned consulting firm CH2M HILL to complete a comprehensive study of the water resources at the Project area. Following a year of analysis, CH2M HILL released its study of the aquifer system in February 2010. Utilizing new models produced by the U.S. Geological Survey in 2006 and 2008, the study estimated the total groundwater in storage in the aquifer system to be between 17 and 34 million acre-feet, a quantity on par with Lake Mead, the nation's largest surface reservoir. The study also identified a renewable annual supply of native groundwater in the aquifer system currently being lost to evaporation. CH2M HILL's findings, which were peer reviewed by leading groundwater experts, confirmed that the aquifer system could sustainably support the Water Project.

Further, and also prior to beginning the formal environmental permitting process, we entered into a Memorandum of Understanding with the Natural Heritage Institute ("NHI"), a leading global environmental organization committed to protecting aquatic ecosystems, to assist with our efforts to sustainably manage the development of our Cadiz/Fenner property. As part of this "Green Compact", we will follow stringent plans for groundwater management and habitat conservation, and create a groundwater management plan for the Water Project.

As discussed in (2), above, we have entered into environmental cost sharing agreements with all participating water providers. The environmental cost sharing agreements created a framework for funds to be committed by each participant to share in the costs associated with the CEQA review work. SMWD served as the lead agency for the review process. ESA Associates, a leading environmental consulting firm, prepared the Water Project's environmental review documentation.

Following a 17 month public review process, SMWD released the Final EIR in July 2012. The Final EIR summarized that, with the exception of unavoidable short-term construction emissions, by implementing the measures developed in the Project's Groundwater Management, Monitoring and Mitigation Plan ("GMMMP"), the Project will avoid significant impacts to desert resources. On July 31, 2012, the SMWD Board of Directors voted unanimously to certify the Final EIR and approve the Project.

Back to Index Following SMWD's action, the San Bernardino County Board of Supervisors voted on October 1, 2012 to approve the GMMMP for the Project and adopted certain findings under CEQA, becoming the first Responsible Agency to take an approving action pursuant to the certified EIR. San Bernardino County served as a Responsible Agency in the CEQA review process as the local government entity responsible for oversight over groundwater resources in the Project area.

Metropolitan Water District of Southern California ("Metropolitan"), also a Responsible Agency, will take action under CEQA prior to construction regarding the terms and conditions of the Project's use of the CRA. Project water supplies will enter Metropolitan's CRA in accordance with its published engineering and design standards and subject to all applicable fees and charges routinely established by Metropolitan for the conveyance of water within its service territory.

(4) Construction and Working Capital

As part of the Water Purchase and Sale Agreement with SMWD referred to in (2), above, SMWD further authorized to continue next steps with the Company, which includes final permitting, design and construction.

As described above, construction of Phase I of the Project would primarily consist of well-field facilities at the Water Project site, a conveyance pipeline extending approximately 43 miles along the right-of-way described in
(1), above, from the well-field to the CRA, and an energy source to pump water through the conveyance pipeline between the Project well-field and the CRA. Existing wells at the Cadiz Valley property currently in use for our agricultural operations will be integrated into the Water Project well-field, reducing the number of wells that must be constructed prior to Project implementation.

The construction of these facilities will require capital financing, which is expected to be entirely provided with lower-cost senior debt, secured by the new facility assets. Our existing Convertible Bond provides us the flexibility to incorporate Water Project construction financing by allowing Project financing to be placed ahead of it in terms of priority.

Existing Pipeline Asset

We currently hold ownership rights to a 96-mile existing idle natural gas pipeline from the Cadiz Valley to Barstow, California that would be converted for the transportation of water.

In September 2011, we entered into two separate agreements with El Paso Natural Gas ("EPNG"), a subsidiary of Kinder Morgan Inc., and Questar Corporation ("Questar") providing us with options to purchase approximately 300-miles of idle, natural gas pipelines for $50 million. The Questar agreement granted us rights to purchase an 80-mile line in Riverside County for $10 million. Based on our evaluation of these lines we allowed the option agreement with Questar to expire and we pursued plans for the EPNG line as described below.

The option agreement with EPNG granted us rights to purchase a 220-mile pipeline between Bakersfield and Cadiz, California for $40 million. Initial feasibility studies indicated that upon conversion the 30-inch line could transport between 20,000 and 30,000 acre-feet of water per year between the Water Project area and various points along the Central and Northern California water transportation network. In February 2012, we made a $1 million payment to EPNG to extend our option to purchase the 220-mile line until April 2013.

Back to Index In December 2012, we entered into a new agreement with EPNG dividing the 220-mile pipeline in Barstow, California, with the Company gaining ownership rights to the 96-mile eastern segment between Barstow and the Cadiz Valley and returning to EPNG rights to the 124-mile western segment for its own use. The 96-mile eastern portion from the Cadiz Valley to Barstow was identified as the most critical segment of the line for accessing the state's water transportation infrastructure. The Barstow area serves as a hub for water delivered from northern and central California to communities in Southern California's High Desert.

In consideration of the new agreement, EPNG reduced the purchase price of the 96-mile eastern segment to a nominal amount of $1 (one dollar), plus previous option payments totaling $1.07 million already made by Cadiz. The remaining purchase price of $1 (one dollar) is payable before expiration of the option period in April 2014. In addition, if EPNG files for regulatory approval of any new use of the 124-mile western segment by December 2015, EPNG will make an additional payment to the Company of $10 million, payable on the date the application for regulatory approval is filed.

The 96-mile Cadiz-Barstow route creates significant opportunities for our water resource development efforts. Once converted to water use, the pipeline can be used to directly connect the Cadiz area to northern and central California water sources, serving a growing need for additional locations for storage of water south of the Bay Delta region. In addition, the 96-mile pipeline creates new opportunities to deliver water, either directly or via exchange, to potential customers in San Bernardino and Kern Counties, areas which do not currently have an interconnection point with the Project. When both the 96-mile line and the 43-mile pipeline to the CRA become operational, the Cadiz Project area would link the two major water delivery systems in California providing flexible opportunities for both supply and storage.

The entire EPNG pipeline was evaluated in the Water Project's EIR during the CEQA process at a programmatic level. Any use of the line would be conducted in conformity with the Project's GMMMP and is subject to further CEQA evaluation (see "Water Resource Development" above).

Agricultural Development

Within the Cadiz/Fenner Property, 9,600 acres have been zoned for agriculture. The infrastructure currently includes seven wells that are interconnected within a portion of this acreage, with total annual production . . .

  Add CDZI to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for CDZI - All Recent SEC Filings
Sign Up for a Free Trial to the NEW EDGAR Online Pro
Detailed SEC, Financial, Ownership and Offering Data on over 12,000 U.S. Public Companies.
Actionable and easy-to-use with searching, alerting, downloading and more.
Request a Trial Sign Up Now


Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.