Form 10-Q for CHENIERE ENERGY PARTNERS, L.P.


3-May-2013

Quarterly Report


ITEM 2. MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF
OPERATION
Information Regarding Forward-Looking Statements This quarterly report contains certain statements that are, or may be deemed to be, "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended (the "Securities Act"), and Section 21E of the Securities Exchange Act of 1934, as amended (the "Exchange Act"). All statements, other than statements of historical fact, included herein or incorporated herein by reference are "forward-looking statements." Included among "forward-looking statements" are, among other things:
• statements regarding our ability to pay distributions to our unitholders;

• statements regarding our expected receipt of cash distributions from Sabine Pass LNG, L.P. ("Sabine Pass LNG") or Sabine Pass Liquefaction, LLC ("Sabine Pass Liquefaction");

• statements regarding future levels of domestic and international natural gas production, supply or consumption or future levels of liquefied natural gas ("LNG") imports into or exports from North America and other countries worldwide, regardless of the source of such information, or the transportation or demand for and prices related to natural gas, LNG or other hydrocarbon products;

• statements regarding any financing transactions or arrangements, or ability to enter into such transactions;

• statements relating to the construction of our natural gas liquefaction trains ("Trains"), including statements concerning the engagement of any engineering, procurement and construction ("EPC") contractor or other contractor and the anticipated terms and provisions of any agreement with any EPC or other contractor, and anticipated costs related thereto;

• statements regarding any agreement to be entered into or performed substantially in the future, including any revenues anticipated to be received and the anticipated timing thereof, and statements regarding the amounts of total LNG regasification, liquefaction or storage capacities that are, or may become, subject to contracts;

• statements regarding counterparties to our commercial contracts, construction contracts and other contracts;

• statements regarding our planned construction of additional Trains, including the financing of such Trains;

• statements that our Trains, when completed, will have certain characteristics, including amounts of liquefaction capacities;

• statements regarding our business strategy, our strengths, our business and operation plans or any other plans, forecasts, projections or objectives, including anticipated revenues and capital expenditures, any or all of which are subject to change;

• statements regarding legislative, governmental, regulatory, administrative or other public body actions, requirements, permits, investigations, proceedings or decisions;

• statements regarding our anticipated LNG and natural gas marketing activities; and

• any other statements that relate to non-historical or future information.

These forward-looking statements are often identified by the use of terms and phrases such as "achieve," "anticipate," "believe," "contemplate," "develop," "estimate," "expect," "forecast," "plan," "potential," "project," "propose," "strategy" and similar terms and phrases, or by the use of future tense. Although we believe that the expectations reflected in these forward-looking statements are reasonable, they do involve assumptions, risks and uncertainties, and these expectations may prove to be incorrect. You should not place undue reliance on these forward-looking statements, which are made as of the date of this quarterly report and speak only as of the date of this quarterly report. Our actual results could differ materially from those anticipated in these forward-looking statements as a result of a variety of factors, including those discussed under "Risk Factors" in our Annual Report on Form 10-K for the year ended December 31, 2012, as amended by Amendment No. 1 on Form 10-K/A. All forward-looking statements attributable to us or persons acting on our behalf are expressly qualified in their entirety by these risk factors. Other than as required under the securities laws, we assume no obligation to update or revise these forward-looking statements or provide reasons why actual results may differ.
As used herein, the terms "Cheniere Partners," "we," "our" and "us" refer to Cheniere Energy Partners, L.P. and its wholly owned subsidiaries.


Introduction

The following discussion and analysis presents management's view of our business, financial condition and overall performance and should be read in conjunction with our Consolidated Financial Statements and the accompanying notes in "Financial Statements and Supplementary Data." This information is intended to provide investors with an understanding of our past performance, current financial condition and outlook for the future. Our discussion and analysis include the following subjects:
• Overview of Business

• Overview of Significant Events

• Liquidity and Capital Resources

• Results of Operations

• Off-Balance Sheet Arrangements

• Summary of Critical Accounting Policies and Estimates

• Recent Accounting Standards

Overview of Business

We are a Delaware limited partnership formed by Cheniere Energy, Inc. ("Cheniere"). Through our wholly owned subsidiary, Sabine Pass LNG, L.P. ("Sabine Pass LNG") we own and operate the regasification facilities at the Sabine Pass LNG terminal located on the Sabine Pass deep water shipping channel less than four miles from the Gulf Coast. The Sabine Pass LNG terminal includes existing infrastructure of five LNG storage tanks with capacity of approximately
16.9 Bcfe, two docks that can accommodate vessels of up to 265,000 cubic meters and vaporizers with regasification capacity of approximately 4.0 Bcf/d. Approximately one-half of the receiving capacity at the Sabine Pass LNG terminal is contracted to two multinational energy companies. We are developing natural gas liquefaction facilities (the "Liquefaction Project") at the Sabine Pass LNG terminal adjacent to the existing regasification facilities through a wholly owned subsidiary, Sabine Pass Liquefaction, LLC ("Sabine Pass Liquefaction"). We plan to construct up to six Trains (each in sequence, "Train 1", "Train 2", "Train 3", "Train 4", "Train 5" and "Train 6"), which are in various stages of development. Nominal capacity for each Train is expected to be approximately 4.5 million metric tons per annum ("mmtpa") of LNG.

Overview of Significant Events

In 2013, and through the filing date of this Form 10-Q, we continue to execute our strategy to operate the Sabine Pass LNG terminal, generate steady and reliable revenues under Sabine Pass LNG's long-term terminal use agreements ("TUAs") and develop and construct the Liquefaction Project.
Our significant accomplishments since January 1, 2013 and through the filing date of this Form 10-Q, include the following:
• In February 2013, Sabine Pass Liquefaction issued an aggregate principal amount of $1.5 billion of 5.625% Senior Secured Notes due 2021 (the "2021 Sabine Pass Liquefaction Notes"). In April 2013, Sabine Pass Liquefaction issued an additional aggregate principal amount of $500.0 million of the 2021 Sabine Pass Liquefaction Notes for an aggregate principal amount of $2.0 billion. In April 2013, Sabine Pass Liquefaction also issued $1.0 billion of 5.625% Senior Secured Notes due 2023 (the "2023 Sabine Pass Liquefaction Notes"). Net proceeds from these offerings are intended to be used to pay capital costs incurred in connection with the construction of Train 1 and Train 2 of the Liquefaction Project in lieu of a portion of the commitments under the Liquefaction Credit Facility described below;

• We entered into a purchase agreement with institutional investors to sell 17.6 million common units for net proceeds, after deducting expenses, of $372.4 million, which includes the general partner's proportionate capital contribution of approximately $7.4 million. We intend to use the proceeds from this offering for costs associated with the Liquefaction Project; and

• Sabine Pass Liquefaction entered into an LNG sale and purchase agreement ("SPA") with Centrica plc that commences upon the date of first commercial delivery for Train 5 and includes an annual contract quantity of 91.25 million MMBtu of LNG and a fixed fee of $3.00 per MMBtu, equating to expected annual contracted cash flow from fixed fees of $274 million.


Liquidity and Capital Resources

Cash and Cash Equivalents

As of March 31, 2013, we had $456.9 million of cash and cash equivalents and $1,719.5 million of restricted cash and cash equivalents.

Sabine Pass LNG Terminal

Regasification Facilities

The Sabine Pass LNG terminal has operational regasification capacity of approximately 4.0 Bcf/d and aggregate LNG storage capacity of approximately 16.9 Bcfe. Approximately 2.0 Bcf/d of the regasification capacity at the Sabine Pass LNG terminal has been reserved under two long-term third-party terminal use agreements ("TUAs"), under which Sabine Pass LNG's customers are required to pay fixed monthly fees, whether or not they use the LNG terminal. Capacity reservation fee TUA payments are made by Sabine Pass LNG's third-party TUA customers as follows:
• Total Gas & Power North America, Inc. ("Total") has reserved approximately
1.0 Bcf/d of regasification capacity and is obligated to make monthly capacity payments to Sabine Pass LNG aggregating approximately $125 million per year for 20 years that commenced April 1, 2009. Total, S.A. has guaranteed Total's obligations under its TUA up to $2.5 billion, subject to certain exceptions; and

• Chevron U.S.A. Inc. ("Chevron") has reserved approximately 1.0 Bcf/d of regasification capacity and is obligated to make monthly capacity payments to Sabine Pass LNG aggregating approximately $125 million per year for 20 years that commenced July 1, 2009. Chevron Corporation has guaranteed Chevron's obligations under its TUA up to 80% of the fees payable by Chevron.

The remaining approximately 2.0 Bcf/d of capacity has been reserved under a TUA by Sabine Pass Liquefaction. Sabine Pass Liquefaction is obligated to make monthly capacity payments to Sabine Pass LNG aggregating approximately $250 million per year, continuing until at least 20 years after Sabine Pass Liquefaction delivers its first commercial cargo at Sabine Pass Liquefaction's facilities under construction, which may occur as early as late 2015. Cheniere Energy Investments, LLC ("Cheniere Investments"), our wholly owned subsidiary, Sabine Pass Liquefaction and Sabine Pass LNG entered into a terminal use rights assignment and agreement ("TURA") pursuant to which Cheniere Investments has the right to use Sabine Pass Liquefaction's reserved capacity under the TUA and has the obligation to make the monthly capacity payments required by the TUA to Sabine Pass LNG. In an effort to monetize Cheniere Investments' reserved capacity under its TURA during construction of the Liquefaction Project, Cheniere Marketing, LLC ("Cheniere Marketing"), a wholly owned subsidiary of Cheniere, has entered into a variable capacity rights agreement ("VCRA") pursuant to which Cheniere Marketing is obligated to pay Cheniere Investments 80% of the expected gross margin of each cargo of LNG that Cheniere Marketing arranges for delivery to the Sabine Pass LNG terminal. The revenue earned by Sabine Pass LNG from the capacity payments made under the TUA and the revenue earned by Cheniere Investments under the TURA are eliminated upon consolidation of our financial statements. We have guaranteed the obligations of Sabine Pass Liquefaction under its TUA and the obligations of Cheniere Investments under the TURA.

In September 2012, Sabine Pass Liquefaction entered into a partial TUA assignment agreement with Total, whereby Sabine Pass Liquefaction will progressively gain access to Total's capacity and other services provided under Total's TUA with Sabine Pass LNG. This agreement will provide Sabine Pass Liquefaction with additional berthing and storage capacity at the Sabine Pass LNG terminal that may be used to accommodate the development of Train 5 and Train 6, provide increased flexibility in managing LNG cargo loading and unloading activity starting with the commencement of commercial operations of Train 3, and permit Sabine Pass Liquefaction to more flexibly manage its LNG storage capacity with the commencement of Train 1. Notwithstanding any arrangements between Total and Sabine Pass Liquefaction, payments required to be made by Total to Sabine Pass LNG shall continue to be made by Total to Sabine Pass LNG in accordance with its TUA.

Under each of these TUAs, Sabine Pass LNG is entitled to retain 2% of the LNG delivered to the Sabine Pass LNG terminal.


Liquefaction Facilities

The Liquefaction Project is being developed at the Sabine Pass LNG terminal adjacent to the existing regasification facilities. We plan to construct up to six Trains, which are in various stages of development. We have commenced construction of Train 1 and Train 2 and the related new facilities needed to treat, liquefy, store and export natural gas. Construction of Train 3 and Train 4 and the related facilities is expected to commence upon, among other things, obtaining financing commitments sufficient to fund construction of such Trains and making a positive final investment decision. We recently began the development of Train 5 and Train 6 and commenced the regulatory approval process in February 2013.

The Trains are being designed, constructed and commissioned by Bechtel Oil, Gas and Chemicals, Inc. ("Bechtel") using the ConocoPhillips Optimized Cascade® technology, a proven technology deployed in numerous LNG projects around the world. Sabine Pass Liquefaction has entered into lump sum turnkey contracts for the engineering, procurement and construction of Train 1 and Train 2 (the "EPC Contract (Train 1 and 2)") and Train 3 and Train 4 (the "EPC Contract (Train 3 and 4)", and together with the EPC Contract (Train 1 and 2), the "EPC Contracts"), with Bechtel in November 2011 and December 2012, respectively.

Sabine Pass Liquefaction has received authorization from the Federal Energy Regulatory Commission (the "FERC") to site, construct and operate Train 1, Train 2, Train 3 and Train 4. Sabine Pass Liquefaction has also received authorization from FERC to begin the pre-filing review process for the development of the additional two Trains. The Department of Energy (the "DOE") has granted Sabine Pass Liquefaction an order authorizing the export of up to the equivalent of 16 mmtpa of LNG to all nations with which trade is permitted.

As of March 31, 2013, the overall project completion for Train 1 and Train 2 was approximately 26% complete, which is significantly ahead of the contractual schedule. Based on our current construction schedule, we anticipate that Train 1 will produce LNG as early as the end of 2015, with Train 2, Train 3, Train 4 and Train 5 expected to commence operations on a staggered basis thereafter. Customers
Sabine Pass Liquefaction has entered into six fixed price, 20-year SPAs that in the aggregate equate to approximately 19.75 mmtpa, which represents approximately 88% of the nominal production capacity of Trains 1 through 5. Under the SPAs, the customers will purchase LNG from us on an FOB basis for a price consisting of a fixed fee plus 115% of Henry Hub per MMBtu of LNG. In certain circumstances, the customers may elect to cancel or suspend deliveries of LNG cargoes, in which case the customers would still be required to pay the fixed fee with respect to cargoes that are not delivered. A portion of the fixed fee will be subject to annual adjustment for inflation. The SPAs and contracted volumes to be made available under the SPAs are not tied to a specific Train; however, the term of each SPA commences upon the start of operations of the specified Train. In aggregate, the fixed fee portion to be paid by these customers is approximately $2.9 billion annually, with fixed fees starting from the commencement of operations of Train 1, Train 2, Train 3, Train 4 and Train 5 equating to approximately $411 million, $564 million, $650 million, $649 million and $588 million, respectively.
To date, we have entered into the following third-party SPAs:
• BG Gulf Coast LNG, LLC ("BG") SPA commences upon the date of first commercial delivery for Train 1 and includes an annual contract quantity of 182,500,000 MMBtu of LNG and a fixed fee of $2.25 per MMBtu and includes additional annual contract quantities of 36,500,000 MMBtu, 34,000,000 MMBtu, and 33,500,000 MMBtu upon the date of first commercial delivery for Train 2, Train 3 and Train 4, respectively, with a fixed fee of $3.00 per MMBtu. The total expected annual contracted cash flow from BG from the fixed fee component is $723 million. In addition, Sabine Pass Liquefaction has agreed to make LNG available to BG to the extent that Train 1 becomes commercially operable prior to the beginning of the first delivery window. The obligations of BG are guaranteed by BG Energy Holdings Limited, a company organized under the laws of England and Wales, with a credit rating of A/A2.

• Gas Natural Aprovisionamientos SDG S.A. ("Gas Natural Fenosa"), an affiliate of Gas Natural SDG, S.A., SPA commences upon the date of first commercial delivery for Train 2 and includes an annual contract quantity of 182,500,000 MMBtu of LNG and a fixed fee of $2.49 per MMBtu, equating to expected annual contracted cash flow from the fixed fee component of $454 million. In addition, we have agreed to make LNG available to Gas Natural Fenosa to the extent that Train 2 becomes commercially operable prior to the beginning of the first delivery window. The obligations of Gas Natural Fenosa are guaranteed by Gas Natural SDG S.A., a company organized under the laws of Spain, with a credit rating of BBB/Baa2.


• Korea Gas Corporation ("KOGAS") SPA commences upon the date of first commercial delivery for Train 3 and includes an annual contract quantity of 182,500,000 MMBtu of LNG and a fixed fee of $3.00 per MMBtu, equating to expected annual contracted cash flow from fixed fees of $548 million. KOGAS is organized under the laws of the Republic of Korea, with a credit rating of A/A1.

• GAIL (India) Limited ("GAIL") SPA commences upon the date of first commercial delivery for Train 4 and includes an annual contract quantity of 182,500,000 MMBtu of LNG and a fixed fee of $3.00 per MMBtu, equating to expected annual contracted cash flow from fixed fees of $548 million. GAIL is organized under the laws of India, with a credit rating of NR/Baa2/BBB-.

• Total, an affiliate of Total S.A., SPA commences upon the date of first commercial delivery for Train 5 and includes an annual contract quantity of 104,750,000 MMBtu of LNG and a fixed fee of $3.00 per MMBtu, equating to expected annual contracted cash flow from fixed fees of $314 million. The obligations of Total are guaranteed by Total S.A., a company organized under the laws of France, with a credit rating of AA/Aa1.

• Centrica plc ("Centrica") SPA commences upon the date of first commercial delivery for Train 5 and includes an annual contract quantity of 91,250,000 MMBtu of LNG and a fixed fee of $3.00 per MMBtu, equating to expected annual contracted cash flow from fixed fees of $274 million. Centrica is registered in England and Wales, with a credit rating of A-/A3/A.

In addition, Cheniere Marketing has entered into an SPA to purchase, at its option, any excess LNG produced that is not committed to non-affiliate parties, for up to a maximum of 104,000,000 MMBtu per annum produced from Train 1 through Train 4. Cheniere Marketing may purchase incremental LNG volumes at a price of 115% of Henry Hub plus up to $3.00 per MMBtu for the first 36,000,000 MMBtu of the most profitable cargoes sold each year by Cheniere Marketing, and then 20% of net profits of the remaining 68,000,000 MMBtu sold each year by Cheniere Marketing.

Construction

In November 2011, Sabine Pass Liquefaction entered into the EPC Contract (Train 1 and 2) with Bechtel. Sabine Pass Liquefaction issued a notice to proceed for construction under the EPC Contract (Train 1 and 2) in August 2012.

In December 2012, Sabine Pass Liquefaction entered into the EPC Contract (Train 3 and 4) with Bechtel. Under the EPC Contract (Train 3 and 4), if Sabine Pass Liquefaction fails to issue notice to proceed to Bechtel by December 31, 2013, then either Sabine Pass Liquefaction or Bechtel may terminate the EPC Contract (Train 3 and 4), and Bechtel will be paid costs reasonably incurred on account of such termination and a lump sum of $5.0 million. The Trains are in various stages of development, as described above.

The total contract price of the EPC Contract (Train 1 and 2) is approximately $3.97 billion, reflecting amounts incurred under change orders through March 31, 2013. Total expected capital costs for Train 1 and Train 2 are estimated to be between $4.5 billion and $5.0 billion before financing costs, including estimated owner's costs and contingencies. The contract price of the EPC Contract (Train 3 and 4) is $3.77 billion, only subject to adjustment by change order (including if Sabine Pass Liquefaction issues the notice to proceed after June 1, 2013). The cost to construct Train 3 and Train 4 is currently estimated to be between $4.5 billion and $5.0 billion before financing costs, including estimated owner's costs and contingencies.

The liquefaction technology to be employed under the EPC Contracts is the ConocoPhillips Optimized Cascade® Process, which was first used at the ConocoPhillips Petroleum Kenai plant built by Bechtel in 1969 in Kenai, Alaska. Bechtel has since designed and/or constructed LNG facilities using the ConocoPhillips Optimized Cascade® technology in Angola, Australia, Egypt, Equatorial Guinea and Trinidad. The design and technology has been proven in over four decades of operation.

Sabine Pass Liquefaction's Trains will require significant amounts of capital to construct and operate and are subject to risks and delays in completion. Even if successfully completed, Train 1 is not expected to operate and generate significant cash flows before the end of 2015.


We currently expect that Sabine Pass Liquefaction's capital resources requirements with respect to Train 1 and Train 2 will be financed through borrowings, equity contributions from us and cash flows under Sabine Pass Liquefaction's SPAs. We believe that with the net proceeds from the issuance of the 2021 Sabine Pass Liquefaction Notes and 2023 Sabine Pass Liquefaction Notes and the construction loans and unfunded commitments under the Liquefaction Credit Facility, Sabine Pass Liquefaction will have adequate financial resources available to complete Train 1 and Train 2 and to meet its currently anticipated capital, operating and debt service requirements through the maturity of its outstanding debt. We currently project that Sabine Pass Liquefaction will generate cash flow from operations by the end of 2015, when Train 1 is anticipated to commence commercial operations, and that such cash flow will be sufficient to meet Sabine Pass Liquefaction's ongoing capital and operating requirements and to pay the interest on our outstanding debt relating to Train 1 and Train 2.

Pipeline Facilities

Cheniere Creole Trail Pipeline, L.P. ("Creole Trail"), an indirect wholly owned subsidiary of Cheniere, owns the Creole Trail Pipeline, a 94-mile pipeline interconnecting the Sabine Pass LNG terminal with a number of large interstate pipelines, including Natural Gas Pipeline Company of America, Transcontinental Gas Pipeline Corporation, Tennessee Gas Pipeline Company, Florida Gas Transmission Company, Texas Eastern Gas Transmission, and Trunkline Gas Company, as well as the intrastate pipeline system of Bridgeline Holdings, L.P.

Sabine Pass Liquefaction has entered into a transportation precedent agreement to secure firm pipeline transportation capacity with Creole Trail and two other pipelines for Train 1 and Train 2. In February 2013, Creole Trail received authorization from the FERC for certain modifications to allow the Creole Trail Pipeline to be able to transport natural gas to the Sabine Pass LNG terminal. Creole Trail estimates the capital costs to modify the Creole Trail Pipeline will be approximately $90 million. The modifications are expected to be in service in time for the commissioning and testing of Train 1 and Train 2.

We have entered into an agreement with Cheniere to purchase the equity interests of the entities that own the Creole Trail Pipeline if, among other things, we obtain acceptable financing for the purchase price. The consideration to be paid by us for the Creole Trail Pipeline is 12 million Class B units and $300 million, plus any costs incurred by Creole Trail from August 2012 until the purchase date, including, if applicable, any portion of the expected $90 million for pipeline modifications.

Capital Resources

Senior Secured Notes

We currently have four series of senior notes outstanding:
•$1,665.5 million of 7½% Senior Secured Notes due 2016 issued by Sabine Pass LNG (the "2016 Notes");
•$420.0 million of 6½% Senior Secured Notes due 2020 issued by Sabine Pass LNG (the "2020 Notes" and collectively with the 2016 Notes, the "Sabine Pass LNG Senior Notes");
•$2,000.0 million of the 2021 Sabine Pass Liquefaction Notes; and
•$1,000.0 million of the 2023 Sabine Pass Liquefaction Notes.

Interest on the 2016 Notes is payable semi-annually in arrears on May 30 and November 30 of each year, interest on the 2020 Notes is payable semi-annually in arrears on May 1 and November 1 of each year, interest on the 2021 Sabine Pass Liquefaction Notes is payable semi-annually in arrears on February 1 and August 1 of each year and interest on the 2023 Sabine Pass Liquefaction Notes is payable semi-annually in arrears on April 15 and October 15 of each year. Subject to permitted liens, the Sabine Pass LNG Senior Notes are secured on a first-priority basis by a security interest in all of Sabine Pass LNG's equity interests and substantially all of Sabine Pass LNG's operating assets, and the 2021 and 2023 Sabine Pass Liquefaction Notes are secured on a first-priority basis by a security interest in all of Sabine Pass Liquefaction's equity interests and substantially all of Sabine Pass Liquefaction's assets.


Sabine Pass LNG may redeem some or all of the 2016 Notes at any time, and from time to time, at a redemption price equal to 100% of the principal plus any accrued and unpaid interest plus the greater of 1.0% of the principal amount of the 2016 Notes or the excess of (i) the present value at such redemption date of the redemption price of the 2016 Notes plus all required interest payments due on the 2016 Notes (excluding accrued but unpaid interest to the redemption date), computed using a discount rate equal to the Treasury Rate as of such . . .

  Add CQP to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for CQP - All Recent SEC Filings
Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.