14-Jan-2013
Regulation FD Disclosure
Portland General Electric Company (PGE or the Company) and the Bonneville Power Administration (BPA) entered into a Memorandum of Understanding (MOU) on January 11, 2013 to pursue modifications to PGE's proposed Cascade Crossing Transmission Project (Cascade Crossing or the Project). Under the modified proposal outlined in the MOU, the Cascade Crossing transmission line would begin at Boardman in northeastern Oregon as originally proposed, but terminate at a new substation 18 miles southwest of Maupin, Oregon. PGE would utilize existing BPA transmission lines from the new substation to Salem, Oregon, rather than extend the Cascade Crossing transmission line to Salem. This would eliminate 101 miles of the project from Maupin to Salem, thereby avoiding most impacts to the Confederated Tribes of Warm Springs Reservation, the Mt. Hood and Willamette national forests and private forest and agricultural land in Marion and Linn Counties, and reducing land acquisition, construction and environmental impacts and resulting mitigation costs.
In addition to construction of the new transmission line, PGE would build the new substation near Maupin, install series capacitors on existing BPA transmission lines and make other enhancements to the regional grid that would increase transmission capacity. In return, PGE would receive certain transmission capacity rights from BPA, with the details of such rights subject to further negotiation. The MOU also provides for the parties to negotiate an exchange whereby PGE would obtain from BPA ownership of additional transmission capacity in exchange for ownership and/or rights to certain PGE assets. Subject to the outcome of negotiations, the modified proposal would provide PGE a total of up to 2,600 MWs of transmission capacity that could be staged to come on-line in phases as needed, both before and after the previously estimated 2017 in-service date. The original scope of the Cascade Crossing project was a 215-mile, 500 kV transmission line that would provide approximately 2,600 MWs of transmission capacity from northeastern Oregon into PGE's service territory in the Willamette Valley near Salem, Oregon. As the parties continue negotiation of the terms and conditions of the modified proposal, the estimated costs and timeline of the proposal will be clarified. The MOU will be available at PGE's website PortlandGeneral.com.
PGE first began developing the Cascade Crossing project in response to an Order issued by the Public Utility Commission of Oregon (OPUC) in 2004 directing the Company to work with BPA and others to develop transmission capacity across the Cascade Mountains. As of December 31, 2012 PGE has incurred approximately $46 million of capital costs related to the project, including costs related to the 101-mile section that would not be constructed under the modified proposal described in the MOU. If definitive agreements are reached with respect to the modified proposal, the Company will seek recovery of all project costs, including those related to the 101-mile section, once the related transmission capacity is available for PGE use. The modified proposal would meet PGE's objective under its Integrated Resource Plan, as most recently acknowledged by the OPUC in November 2010, of providing additional transmission capacity from northeastern Oregon into PGE's service territory in the Willamette Valley.
|
|