Other Events
Neal Hot Springs, Oregon
All three modules are operating and for the past three days have averaged 22.4 net megawatts per operating hour (31.5 gross megawatts). Module 1 has been in operation for 44 days, Module 2 has operated for 48 days and Module 3 with 8 days of operation. Under the terms of the Power Purchase Agreement with Idaho Power Company, November and December generation is paid at a seasonally adjusted price of $115.20 per megawatt-hour, which is 120 percent of the 2012 contract price.
The equipment supply contractor has stated its intention to commence required plant performance testing this week. The contractor has experienced certain project delays and is now under notice to complete the project within the required schedule. Project completion includes milestone activities related to testing and completion of a list of work items.
San Emidio, Nevada
Since performance testing was concluded in October, the San Emidio power plant has continued to operate on a normal basis. In November the plant averaged 9.42 net megawatts per operating hour (12.41 gross megawatts) and achieved 94.6 percent availability for the month of November. December operations were interrupted for three days due to the failure of an electrical component in a variable frequency drive. The plant has averaged 9.65 net megawatts per operating hour at 82.2 percent availability for December to date.
Work continues on finalizing a long term loan which is now anticipated to close in January, the proceeds of which will repay the construction loan for San Emidio. Prior to closing the anticipated long term loan, the following items must be completed: (i) finalizing the project lender's independent engineering reservoir and project reports, (ii) obtaining acceptable manufacturer/contractor support for certain turbine/gearbox vibration previously identified and addressed by the contractor (for more discussion, se the Form 10-Q for the period ended September 30, 2012), and (iii) completing final commercial settlement with the engineering, procurement and construction contractor.
In mid-November, USG Nevada LLC received its $10.7 million cash grant from the
U.S. Department of Treasury. The cash grant is for Specified Energy Property in
Lieu of Tax/Credits relating to the San Emidio geothermal power plant under
Section 1603, Division B of the American Recovery and Reinvestment Act of 2009.
An existing $7.5 million bridge loan and its associated administrative costs
were paid in full with the balance of $2.9 million retained by the Company.
Raft River, Idaho
Raft River has operated continuously through the quarter with 99.5 percent operating availability and has averaged 9.61 megawatts per operating hour. The plant achieved 100 percent operating availability for both October and November. Due to warmer than normal fall and winter temperatures, power generation this year has been less than average.
|
|