14-Nov-2012

Quarterly Report


Item 2. Management's Discussion and Analysis of Financial Condition and Results of Operations

Note Regarding Forward-Looking Statements

This quarterly report on Form 10-Q and other reports filed by the Company from time to time with the SEC (collectively the "Filings") contain or may contain forward-looking statements and information that are based upon beliefs of, and information currently available to, Company's management as well as estimates and assumptions made by Company's management. Readers are cautioned not to place undue reliance on these forward-looking statements, which are only predictions and speak only as of the date hereof. When used in the filings, the words "anticipate", "believe", "estimate", "expect", "future", "intend", "plan", or the negative of these terms and similar expressions as they relate to Company or Company's management identify forward-looking statements. Such statements reflect the current view of Company with respect to future events and are subject to risks, uncertainties, assumptions, and other factors (including the statements in the section "results of operations" below), and any businesses that Company may acquire. Should one or more of these risks or uncertainties materialize, or should the underlying assumptions prove incorrect, actual results may differ significantly from those anticipated, believed, estimated, expected, intended, or planned.

Although the Company believes the expectations reflected in the forward-looking statements are based on reasonable assumptions, the Company cannot guarantee future results, levels of activity, performance, or achievements. Except as required by applicable law, including the securities laws of the United States, the Company does not intend to update any of the forward-looking statements to conform these statements to actual results. Readers are urged to carefully review and consider the various disclosures made throughout the entirety of this report, which attempts to advise interested parties of the risks and factors that may affect our business, financial condition, results of operations, and prospects.

Our financial statements are prepared in US Dollars and in accordance with accounting principles generally accepted in the United States. See "Foreign Currency Translation and Comprehensive Income (Loss)" below for information concerning the exchange rates at which Renminbi ("RMB") were translated into US Dollars ("USD") at various pertinent dates and for pertinent periods.

OVERVIEW OF BUSINESS BACKGROUND

The Company was incorporated on May 8, 1980, under the laws of the State of Colorado. On September 6, 2001, the Company re-domiciled its state of incorporation from Colorado to Nevada. The Company, through its subsidiaries Shanghai TCH Energy Technology Co., Ltd. ("Shanghai TCH") and Huahong New Energy Technology Co, Ltd, sells and leases energy saving systems and equipment to our customers. On March 8, 2007, the Company changed its name to "China Recycling Energy Corporation."

In September 2001, Boulder Brewing changed its state of incorporation from Colorado to Nevada and its name to Boulder Acquisitions, Inc., or Boulder Acquisitions. From the date of reincorporation until June 23, 2004, Boulder Acquisitions had no material operations or assets.

On June 23, 2004, we completed a stock exchange with the stockholders of Sifang Holdings Co., Ltd. ("Sifang Holdings"). The exchange was consummated under Nevada and Cayman Islands law pursuant to the terms of a Securities Exchange Agreement, dated June 23, 2004 by and among Boulder Acquisitions, Sifang Holdings and the stockholders of Sifang Holdings. Pursuant to the Securities Exchange Agreement, we issued 13,782,636 shares of our common stock to the stockholders of Sifang Holdings, 89.7% of our post-exchange issued and outstanding common stock, for 100% of the outstanding capital stock of Sifang Holdings.

Effective August 6, 2004, we changed our name from Boulder Acquisitions, Inc. to China Digital Wireless, Inc. From August 2004 to December 2006, we primarily engaged in pager and mobile phone distribution and provided value added information services to the customers in the People's Republic of China ("PRC"). We phased out and scaled down our operations in the mobile phone distribution business and the pager and mobile phone value-added information services, and, on May 10, 2007, the Company approved and announced it discontinued these businesses.

In December 2006, we began to conduct business in the energy saving and recycling industry, including purchasing equipment, devices, hardware and software for the construction and installation of TRT systems and other renewable energy products. TRT is an electricity generating system that utilizes the exhaust pressure and heat produced in the blast furnace of steel mills to generate electricity. It has commercial value for steel mills by using waste heat and steam to produce electricity for the operation of the mills.

-27-

Our current business is primarily conducted through our wholly-owned subsidiary, Sifang Holdings, its wholly-owned subsidiaries, Huahong New Energy Technology Co., Ltd. ("Huahong") and Shanghai TCH, Shanghai TCH's wholly-owned subsidiaries, Xi'an TCH Energy Technology Company, Ltd ("Xi'an TCH") and Xingtai Huaxin Energy Tech Co., Ltd. ("Huaxin"), and Xi'an TCH's subsidiary Erdos TCH Energy Saving Development Co., Ltd ("Erdos TCH"), in which 90% of the investment will be from Xi'an TCH, a joint venture between Xi'an TCH and Erdos Metallurgy Co., Ltd. Shanghai TCH was established as a foreign investment enterprise in Shanghai under the laws of the PRC on May 25, 2004, currently with registered capital of $29.80 million. Xi'an TCH was incorporated in Xi'an, Shaanxi Province under the laws of the PRC on November 8, 2007. Huaxin was incorporated in Xingtai, PRC in November 2007. Erdos TCH was incorporated in April 2009. Huahong was incorporated in February 2009.

Hebei Xingtai Steel Group Project

On April 8, 2007, our Board of Directors approved and made effective a TRT Project Joint-Operation Agreement ("Joint-Operation Agreement") which was conditionally entered into on February 1, 2007 between Shanghai TCH and Xi'an Yingfeng Science and Technology Co., Ltd. ("Yingfeng"). Under the Joint-Operation Agreement, Shanghai TCH and Yingfeng jointly pursued a project to design, construct, install and operate two TRT systems for Xingtai Iron and Steel Company, Ltd. ("Xingtai"). These two projects were completed and put into operation in February and August 2007, respectively. On October 31, 2007, Shanghai TCH entered an asset-transfer agreement with Yingfeng. The terms and conditions of this agreement required the transfer of all electricity-generating related assets owned by Yingfeng to Shanghai TCH. As a result, the contractual relationships between Shanghai TCH and Yingfeng under the TRT Project Joint-Operation Agreement were terminated.

Shengda Project

On March 15, 2011, the Company incorporated a new wholly owned subsidiary Pingshan County Shengda Energy Technology Co., Ltd ("Shengda"). Xi'an TCH contributed cash of $4,559,271 (RMB 30,000,000) into Shengda as initial capital. Shengda was set up to undertake waste energy recycling projects from a steel and chemical company in Pingshan County in accordance with and pursuant to a Recycling Economy Projects Cooperative Framework Agreement entered into by the parties. However, final terms for the projects were not reached, and, as a result, Shengda was not operational. In July 2012, Shengda applied for cancellation of its registration with the appropriate authorities. In September 2012, Shengda was liquidated and deregistered.

Shanxi Zhangzhi Steel Group Project

Under the Joint-Operation Agreement discussed above, Shanghai TCH and Yingfeng also jointly pursued a project, which was entered into between Yingfeng and Zhangzhi Iron and Steel Company, Ltd. ("Zhangzhi") on June 22, 2006, to design, construct, install and operate a TRT system for Zhangzhi Iron. Shanghai TCH provided various investments and properties for the project including cash, hardware, software, equipment, major components and devices. In return, Shanghai TCH obtained all the rights, titles, benefits and interests that Yingfeng originally had under the Project Contract, including but not limited to the regular cash payments made by Xingtai and other property rights and interests. On October 31, 2007, Shanghai TCH acquired this contract as part of its asset-transfer agreement with Yingfeng as discussed above. According to the transferred contracts, Shanghai TCH installed and owns a TRT system and leases it to Zhangzhi for 13 years, from July 25, 2007 to July 25, 2020. During the lease, Zhangzhi will pay Shanghai TCH a monthly rent of $0.16 million (RMB 1.1 million). After the lease expires and all rents owed are paid, Shanghai TCH will transfer the title of the system to Zhangzhi free of charge.

Shengwei Group - Tong Chuan Project

In November 2007, Shanghai TCH signed a cooperative agreement with Shengwei Group to build two sets of 12MW cement low temperature heat power generation systems for Shengwei's two 2,500-tons-per-day cement manufacturing lines in Jing Yang and for a 5,000-tons-per-day cement manufacturing line in Tong Chuan. At the end of 2008, construction of the cement low temperature heat power generation in Tong Chuan was completed at a cost of $6,191,000 (RMB 43,000,000) and put into operation. Under the original agreement, the ownership of the cement low temperature heat power generation systems would belong to Shengwei from the date the projects were put into service. Shanghai TCH is responsible for the daily maintenance and repair of the projects, and charges Shengwei a monthly electricity fee based on the actual power generated by the projects at
0.4116 RMB per KWH for an operating period of five years with the assurance from Shengwei of a properly functioning 5,000-tons-per-day cement manufacturing line and not less than 7,440 heat hours per year for the electricity generator system. Shengwei Group collateralized the cement manufacturing line in Tong Chuan to guarantee its obligations to provide the minimum electricity income from the power generator system under the agreement during the operating period. At the end of the five-year operating period, Shanghai TCH will have no further obligations under the cooperative agreement. On May 20, 2009, Shanghai TCH entered into a supplementary agreement with Shengwei Group to change the timing of title transfer to Shenwei from the date the projects put into operation to the end of the lease term. In addition, the supplementary agreement provided that Shanghai TCH will charge Shengwei based on actual power usage subject to a minimum of $0.31 million (RMB 2.1 million) per month during the operating period (lease term).

-28-

Shengwei Group - Jing Yang Project

On June 29, 2009, construction of the cement low temperature heat power generation system in Jing Yang was completed at a cost of $7,318,000 (RMB 50,000,000) and put into operation. Shanghai TCH charges Shengwei a technical service fee of $336,600 (RMB 2,300,000) monthly for the 60 months of the lease. Shengwei has the right to purchase the cement low temperature heat power generation system for $29,000 (RMB 200,000) at the end of the lease. Shengwei is required to provide assurance of properly functioning two 2,500-tons-per-day cement manufacturing lines and not less than 7,440 heat hours per year for the cement low temperature heat power generation. Shengwei Group collateralized the cement manufacturing lines in Jing Yang to guarantee its obligations to provide the minimum electricity income from the waste energy power generator system under the agreement during the operating period. Effective July 1, 2009, Shanghai TCH outsourced the operation and maintenance of the cement low temperature heat power generation systems in Tong Chuan and JinYang to a third party for $732,000 (RMB 5,000,000) per year.

Shenmu Project

On September 30, 2009, Xi'an TCH delivered to Shenmu County Jiujiang Trading Co., Ltd. ("Shenmu") a set of three 6 MW capacity waste gas power generation systems pursuant to a Cooperative Contract on Coke-oven Gas Power Generation Project (including its Supplementary Agreement) and a Gas Supply Contract for Coke-oven Gas Power Generation Project (the "Contracts"). The Contracts are for 10 years and state that Xi'an TCH will recycle coke furnace gas from the coke-oven plant of Shenmu to generate power, which will be supplied back to Shenmu. Shenmu agreed to supply Xi'an TCH the coke-oven gas free of charge. Under the Contracts, Shenmu will pay Xi'an TCH an annual "energy-saving service fee" of approximately $5.6 million in equal monthly installments for the life of the contracts, as well as such additional amount as may result from the supply of power to Shenmu in excess of 10.8 million kilowatt hours per month. We are responsible for operating the projects and will do so through an unrelated third party. Shenmu guarantees that monthly gas supply will not be less than 21.6 million standard cubic meters. If gas supply is less, Shenmu agrees to pay Xi'an TCH the energy-saving service fee described above for up to 10.8 million kilowatt-hours per month. Xi'an TCH maintains the ownership of the project throughout the term of the contracts, including the already completed investment, design, equipment, construction and installation as well as the operation and maintenance of the project. At the end of the 10-year term, ownership of the projects transfers to Shenmu at no charge. Shenmu provided a lien on its production line to guarantee its performance under the Contracts. Shenmu's three major stockholders provided an unlimited joint liability guarantee to Xi'an TCH for Shenmu's performance under the Contracts and the Yulin Huiyuan Group, an independent third party, provides a guarantee to Xi'an TCH for Shenmu's performance under the Contracts.

On December 31, 2011, Xi'an TCH entered into a Repurchase Agreement for the Coke-Oven Gas Power Generation Project (the "Repurchase Agreement") with Shenmu. Under the Repurchase Agreement, Shenmu will purchase the set of 18MW capacity power generating systems (the "Systems") from Xi'an TCH and pay outstanding energy saving service fees of $3.08 million (RMB 19.44 million) to Xi'an TCH within three working days from the date of the Repurchase Agreement. Xi'an TCH will transfer the Systems to Shenmu for $18.75 million (RMB 120 million) (the "Repurchase Price") to be paid in three installments within 180 days. In June 2012, the Company received the full payment of the outstanding energy saving service fees and system repurchase price, and, as a result, ownership of the Systems was transferred to Shenmu and the Cooperative Contract was terminated.

Erdos Projects

On April 14, 2009, the Company incorporated a joint venture ("JV") with Erdos Metallurgy Co., Ltd. ("Erdos") to recycle waste heat from Erdos' metal refining plants to generate power and steam, which will then be sold back to Erdos. The name of the JV is Inner Mongolia Erdos TCH Energy Saving Development Co., Ltd ("Erdos TCH") with a term of 20 years, and initial registered capital of $2,635,000 (RMB 18,000,000). As of September 30, 2012, total registered capital was increased to $17.55 million (RMB 120 million), of which $16.37 million (RMB 112 million) was contributed by Xi'an TCH and $1.18 million (RMB 8 million) was from Erdos Metallurgy. Total investment for the project is estimated at $79 million (RMB 500 million) with an initial investment of $17.55 million (RMB 120,000,000). As of September 30, 2012, Erdos contributed 7% of the total investment of the project, and Xi'an TCH contributed 93%. With respect to profit distribution, Xi'an TCH and Erdos will receive 80% and 20% of the profit from the JV, respectively, until Xi'an TCH has received the complete return of its investment. Xi'an TCH and Erdos will then receive 60% and 40% of the profit from the JV, respectively. The profits to be distributed will be computed based on Chinese generally accepted accounting principles. The principal difference between US GAAP and Chinese GAAP with regards to the Erdos TCH project is that a sales-type lease under US GAAP is treated as an operating lease under Chinese GAAP. When the term of the JV expires, Xi'an TCH will transfer its equity in the JV to Erdos at no additional cost.

On April 18, 2009, Erdos TCH signed a Cooperation Agreement with Erdos to recycle heat from groups of furnaces of Erdos Metallurgy's metal refining plants to generate power and steam, which will then be sold back to Erdos Metallurgy. According to the contract, Erdos TCH will install a group of power generation projects with a total of 70MW power capacity, which may expand up to 120MW, and 30-ton steam per hour, with an estimated total investment in excess of $79 million (RMB 500 million). The construction of the projects was split into three phases, two power generation systems in Phase I with a total of 18MW power capacity, three power generation systems in Phase II with a total of 27MW power capacity and one power generation system in Phase III with 25MW power capacity.

-29-

At the end of 2009, Erdos TCH completed the first 9MW power station of Phase I of the project and put it into operation. At the end of March 2010, Erdos TCH completed the construction of Phase I through completion of the second 9MW power station and delivery of the units for operation. Phase I includes two 9MW systems for a combined 18MW power capacity. Pursuant to the Co-operation Agreement and the supplement agreements signed between Erdos and Erdos TCH, Erdos shall purchase all the electricity and steam to be generated from the JV's power generation systems. Erdos TCH leased the two 9MW systems to Erdos and is responsible for their operation and maintenance. For each phase of the project, the lease term is 20 years starting from the date of completion of the phase. Erdos agreed to pay a fixed minimum of $0.24 million (RMB 1.5 million) per month for each 9MW capacity power generation system. In addition Erdos will pay the actual amount if the actual sale of the electricity generated is more than $0.24 million (RMB 1.5 million) monthly per unit. Effective January 2010 and April 2010 respectively, Erdos TCH outsourced to an independent third party the operation and maintenance of the two 9MW power generation projects for $995,000 (RMB 6.27 million) each per year. After 20 years, the units will be transferred to Erdos without any charge. During the fourth quarter of 2010, Erdos power generation system Phase II, two 9MW capacity electricity power generation system was completed and put into operation. During the first quarter of 2011, Erdos power generation system Phase II the 3rd 9MW capacity electricity power generation system was completed and put into operation through sales type lease with terms similar to the Phase I project.

In September 2012, Erdos TCH, Erdos and general contractor Xianyang Hengfeng Energy Engineering Co., Ltd ("Hengfeng") entered into an agreement to terminate the construction of Phase III of the power generation system projects due to the fact that Erdos stopped construction of the refining plant as a result of a change in business strategy. Cost of construction in progress which Erdos TCH paid for Phase III of the project was $19.86 million (RMB 125.44 million) at termination date, Hengfeng returned $13.72 million (RMB 86.70 million) to Erdos TCH towards payments made for construction in progress; and Erdos compensated $3.58 million (RMB 22.04 million) to Erdos TCH for the loss, Erdos TCH in turn paid $0.32 million (RMB 2.0 million) to Hengfeng for the loss from the project termination; accordingly, Erdos incurred a net loss of $2.96 million (RMB 18.74 million) from the termination of this project.

Pucheng Biomass Project

On January 20, 2010, Xi'an TCH entered into a Technical Reconstruction Letter of Intent with Xueyi Dong ("Dong") a natural person with Chinese citizenship for Xi'an TCH reconstructing and transforming a Thermal Power Generation System owned by Dong into a 12MW Biomass Power Generation Systems ("Biomass Systems" or "BMPG") for $2.2 million (RMB 15 million), of which, $1.03 million (RMB 7 million) was payable to Dong, and $1.18 million (RMB 8 million) to one of the Company's shareholders, who had previously paid that amount to Dong on behalf of the Company.

After the successful transformation of the systems, Xi'an TCH entered into a Biomass Power Generation Asset Transfer Agreement (the "Transfer Agreement") with Dong on June 29, 2010. Under the Transfer Agreement, Dong transferred the Biomass Systems to Xi'an TCH, and Xi'an TCH was to pay Dong $14,705,900 (RMB 100,000,000) for the systems, including RMB 20,000,000 in cash and RMB 80,000,000 in shares of the Company's common stock. As of December 31, 2011, the Company paid the consideration (including the cash portion) in full. On November 22, 2011, our Board of Directors approved the issuance of 2,941,176 shares of the Company's common stock to Dong at $4 per share. These shares have piggy back registration rights and are subject to a one year lock-up period. The shares issued to Dong were included in a Form S-3 Registration Statement, as amended, that we initially filed with the SEC on February 22, 2012 and amended on April 12, 2012 and May 7, 2012. The resale Form S-3 Registration Statement was declared effective by the SEC on May 18, 2012.

On June 29, 2010, Xi'an TCH entered into a Biomass Power Generation Project Lease Agreement with Pucheng XinHengYuan Biomass Power Generation Co., Ltd., ("XHY"). Under this lease, Xi'an TCH leased this same set of 12MW biomass power generation systems to XHY at a minimum of $279,400 (RMB 1,900,000) per month for 15 years. The leasing fee will increase proportionately with the biomass generated electricity fee in China during the term of this lease agreement.

-30-

Zhongbao Project

On September 30, 2010, Xi'an TCH delivered to Zhongbao Binhai Nickel Co., Ltd. ("Zhongbao") a set of 7MW capacity Waste Heat Power Generation ("WHPG") systems, which are integral parts of the facilities designed to produce 80,000 tons of nickel-alloy per year according to the recovery and power generation of the waste heat agreement with Zhongbao, an agreement that was transferred from China Zhonggang Binhai Enterprise Ltd. ("Zhonggang") in July 2009. Zhongbao is a nickel-alloy manufacturing joint venture between Zhonggang and Shanghai Baoshan Steel Group that was established in June 2009. Total investment in this project was approximately $7.8 million (RMB 55 million). The Contract is for nine years and states that Xi'an TCH will recycle waste heat from the nickel-alloy rotary kilns of Zhongbao to generate power and steam, which will be supplied back to Zhongbao, and help to reduce over 20,000 tons of carbon dioxide emissions every year. By the end of the term, the system shall be transferred to Zhongbao at RMB
1. Under the Contracts, Zhongbao will pay the Company a monthly "energy-saving service fee" based on the volume of the electricity and steam generated from the WHPG system in the prior month within the first five days of each month at a pre-agreed price, but no less than the minimum monthly payment of $238,000 (RMB 1.5 million). Zhongbao agrees to supply Xi'an TCH the nickel-alloy rotary kilns gas, water and compressed air free of charge, except salty water at $1.00 (RMB 6.3) per ton. Zhongbao also guarantees to continuously supply not less than 6,800 heat hours per year for the WHPG, or the operating term will be extended accordingly. Xi'an TCH outsourced its operation and maintenance works to a third party for annual payments of $380,000 (RMB 2.4 million) for the whole operation period. In addition, Xi'an TCH shall be responsible for applying the Clean Development Mechanism ("CDM") and the net proceeds from CDM will be distributed between Zhongbao and Xi'an TCH at 60% and 40%, respectively. As of September 30, 2012, Xi'an TCH had not yet commenced the CDM application process.

In June 2011, the system of the project ZhongBao was sold to and leased back from Cinda Financial Leasing Co., Ltd. (the "Cinda Financial"), the Company engaged a third party guarantee company as the guarantor for the loan, which was approved by the Industrial Bank on July 1, 2011.

Shanxi Datong Coal Group Power Generation Projects

In February 2011, Xi'an TCH signed a contract with Shanxi Datong Coal Group Steel Co., Ltd (the "Shanxi Datong") to recycle gas and steam from groups of blast-furnaces and converter of Shanxi Datong's metal refining plants to generate power. According to the contract, Xi'an TCH will install two 3MW TRT, one 15MW WGPG and two 1MW steam power generation systems, with a total of 23MW power capacity for an estimated total investment of $28.57 million (RMB 180 million). The lease term is 30 years. During the lease term, Shanxi Datong will be responsible for operating the projects and pay service fee to Xi'an TCH. The service fee is based on an average of 8,000 electricity-generating hours per year and $0.05 (RMB 0.33) per kilowatt hour ("Kwh") for the first five years from the completion of each power generation station. For each of the leases, at the 6th year, 11th year and 21st year thereafter, the rate will be RMB 0.3 Kwh,
0.27 Kwh and 0.25 Kwh, respectively. After 30 years, the units will be transferred to Shanxi Datong without any charge.

On February 28, 2011, Xi'an TCH entered into an agreement with Xi'an Huaxin Energy Tech Co., Ltd (the contractor for construction) for Shanxi Datong Coal projects of two 3MW TRT and one 15MW WGPG systems described above.

As of September 30, 2012, the Company had paid $15.50 million for Shanxi Datong Coal Group Power Generation project. The Company is committed to pay an additional $12.80 million for the Shanxi Datong Coal Group Power Generation project. The project was previously halted due to business reorganization of Shanxi Datong and a renegotiation of one of the power stations with Xi'an TCH to amend certain construction plans. The construction of this project was resumed in April 2012 and the Company expects to complete one of the power stations by the end of 2012.

Shenqiu Yuneng Biomass Power Generation Projects

On May 25, 2011, Xi'an TCH entered into a Letter of Intent with Shenqiu YuNeng Thermal Power Co., Ltd. (the "Shenqiu") for Xi'an TCH to reconstruct and transform a Thermal Power Generation System owned by Shenqiu into a 75T/H Biomass Power Generation System for $3.57 million (RMB 22.5 million). The project commenced in June 2011, and was completed in the third quarter of 2011. On September 28, 2011, Xi'an TCH entered into a Biomass Power Generation Asset Transfer Agreement with Shenqiu. Per the Transfer Agreement, Shenqiu sold to Xi'an TCH a set of 12 MW biomass power generation systems, effectuation of such sale occurring after Xi'an TCH converted the system for biomass power generation purposes. As consideration for the biomass power generation system, Xi'an TCH agreed to pay Shenqiu $10,937,500 (RMB 70 million) in cash in three installments within six months upon the transfer of ownership of the system. As of September 30, 2012, all of the consideration had been paid in full. On September 28, 2011, Xi'an TCH and Shenqiu also entered into a Biomass Power Generation Project Lease Agreement (the "Lease Agreement"). Under the Lease Agreement, Xi'an TCH agreed to lease the set of 12MW biomass power generation systems to Shenqiu for $286,000 (RMB 1,800,000) per month for a term of 11 years. Upon completion of the Lease Agreement, ownership of this system will be transferred from Xi'an TCH to Shenqiu at no cost. Shenqiu provided one month leasing fee as security deposit to Xi'an TCH as well as personal guarantees from its legal representative.

Related Party Transactions

Erdos TCH sold all power generation stations through sales type leases to Erdos Metallurgy Co., Ltd., the non-controlling interest holder. Total sales and interest income for this non-controlling interest was $0.66 million and $5.53 million for the nine months ended September 30, 2012, and $11.66 million and $5.09 million for the nine months ended September 30, 2011; $0.28 million and . . .

  Add CREG to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for CREG - All Recent SEC Filings
Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.