Item 2. Management's Discussion and Analysis of Financial Condition and Results of Operations

Cautionary Comment Regarding Forward-Looking Statements

This Report includes statements that are, or may be considered to be, "forward-looking statements" within the meaning of Section 27A of the Securities Act of 1933, as amended, or the Securities Act, and Section 21E of the Securities Exchange Act of 1934, as amended, or the Exchange Act. These forward-looking statements are included throughout this Report, including in this section, "Management's Discussion and Analysis of Financial Condition and Results of Operations," and relate to matters such as our industry, business strategy, goals and expectations concerning our market position, future operations, margins, profitability, capital expenditures, liquidity and capital resources and other financial and operating information. We have used the words "anticipate," "assume," "believe," "budget," "continue," "could," "estimate," "expect," "forecast," "future," "intend," "may," "plan," "potential," "predict," "project," "should," "will," "would" and similar terms and phrases to identify forward-looking statements in this Report.

Forward-looking statements reflect our current expectations as of the date of this Report regarding future events, results or outcomes. These expectations may or may not be realized. Some of these expectations may be based upon assumptions or judgments that prove to be incorrect. In addition, our business and operations involve numerous risks and uncertainties, many of which are beyond our control, that could result in our expectations not being realized or otherwise could materially affect our financial condition, results of operations and cash flows.

Actual events, results and outcomes may differ materially from our expectations due to a variety of factors. Although it is not possible to identify all of these factors, they include, among others, the following:

changes in general economic conditions, including recessions, reductions in federal, state and local government funding for infrastructure services and changes in those governments' budgets, practices, laws and regulations;

delays or difficulties related to the completion of our projects, including additional costs, reductions in revenues or the payment of liquidated damages, or delays or difficulties related to obtaining required governmental permits and approvals;

actions of suppliers, subcontractors, design engineers, joint venture partners, customers, competitors, banks, surety companies and others which are beyond our control, including suppliers', subcontractors', and joint venture partners' failure to perform;

the effects of estimates inherent in our percentage-of-completion accounting policies, including onsite conditions that differ materially from those assumed in our original bid, contract modifications, mechanical problems with our machinery or equipment and effects of other risks discussed in this document;

design/build contracts which subject us to the risk of design errors and omissions;

cost escalations associated with our contracts, including changes in availability, proximity and cost of materials such as steel, cement, concrete, aggregates, oil, fuel and other construction materials, and cost escalations associated with subcontractors and labor;

our dependence on a limited number of significant customers;

adverse weather conditions; although we prepare our budgets and bid contracts based on historical rain and snowfall patterns, the incidence of rain, snow, hurricanes, etc., may differ materially from these expectations;

the presence of competitors with greater financial resources or lower margin requirements than ours, and the impact of competitive bidders on our ability to obtain new backlog at reasonable margins acceptable to us;

our ability to successfully identify, finance, complete and integrate acquisitions;

citations issued by any governmental authority, including the Occupational Safety and Health Administration;

federal, state and local environmental laws and regulations where non-compliance can result in penalties and/or termination of contracts as well as civil and criminal liability;

the instability of certain financial institutions, which could cause losses on our cash and cash equivalents and short-term investments;

adverse economic conditions in our markets; and

the other factors discussed in more detail in our Annual Report on Form 10-K for the year ended December 31, 2011 ("2011 Form 10-K") under "Item 1A. -Risk Factors."

In reading this Report, you should consider these factors carefully in evaluating any forward-looking statements and you are cautioned not to place undue reliance on any forward-looking statements. Although we believe that our plans, intentions and expectations reflected in, or suggested by, the forward-looking statements that we make in this Report are reasonable, we can provide no assurance that they will be achieved.


The forward-looking statements included in this Report are made only as of the date of this Report, and we undertake no obligation to update any information contained in this Report or to publicly release the results of any revisions to any forward-looking statements to reflect events or circumstances that occur, or that we become aware of after the date of this Report, except as may be required by applicable securities laws.

Overview

Sterling is a leading heavy civil construction company that specializes in the building, reconstruction and repair of transportation and water infrastructure. Transportation infrastructure projects include highways, roads, bridges, light rail and commuter rail, foundations and structures. Water infrastructure projects include water, wastewater and storm drainage systems. Sterling provides general contracting services, including excavating, concrete and asphalt paving, installation of large-diameter water and wastewater distribution systems, construction of bridges and similar large structures, construction of light and commuter rail infrastructure, concrete and asphalt batch plant operations, concrete crushing and aggregates operations. Sterling performs the majority of the work required by its contracts with its own crews and equipment.

Sterling has grown its operations by expanding both its service profile and market areas. This involved adding services, such as concrete operations, in order to capture a greater percentage of available work in current and potential markets. It also involved strategically expanding operations, either by establishing a branch office in a new market, often after having successfully bid on and completed a project in that market, or by acquiring a company that gives us an immediate entry into a market. Sterling extended both its service profile and its geographic market reach with the 2009 acquisition of Ralph L. Wadsworth Construction Company, LLC ("RLW"), which has operations primarily in Utah, and the 2011 acquisitions of J. Banicki Construction, Inc. ("JBC") and Myers & Sons Construction, L.P. ("Myers") with operations in Arizona and California, respectively.

Sterling operates primarily in Texas, Utah, Nevada, Arizona and California, states that management believes benefit from both positive long-term demographic trends as well as a historical commitment to funding transportation and water infrastructure projects. Currently, the Company also has highway construction contracts in Hawaii, Montana and Louisiana. From 2005 to 2010, the populations of Texas, Utah, Nevada, Arizona and California grew 10.2%, 15.8%, 14.8%, 9.1% and 3.5%, respectively, compared to approximately 4.5% for the national average. While the near-term funding available for infrastructure spending in these markets is currently limited, management anticipates that long-term population growth and increases in required spending for infrastructure in these markets will positively affect business opportunities over the coming years.

For a more detailed discussion of the Company's business, readers of this report are advised to review "Item 1, Business," of the 2011 Form 10-K.

For purposes of the discussions which follow, "Current Quarter" refers to the three month period ended September 30, 2012, "Prior Quarter" refers to the three month period ended September 30, 2011, "Current Period" refers to the nine month period ended September 30, 2012 and "Prior Period" refers to the nine month period ended September 30, 2011.

Financial Results for the Current Period, Operational Issues and Outlook for 2012 Financial Results

As discussed further in the 2011 Form 10-K, the Company's 2011 results were well below those of 2010 as a result of a pre-tax charge of $67.0 million related to the impairment of goodwill and a decline in our overall margins which were adversely affected by production issues on a number of construction projects, primarily in the fourth quarter of 2011. These declines were in part a result of revisions to estimated profitability on construction projects, both favorable and unfavorable, which resulted in a net pre-tax charge of $11.8 million in 2011.

In the Current Quarter and Current Period, the Company had operating income of $4.2 million and $7.9 million, respectively, and net income (loss) attributable to Sterling common stockholders of $1.0 million and $(3.2) million, respectively. Included in the net loss attributable to Sterling common stockholders for the Current Period is additional earnings allocated to noncontrolling interest owners of $6.7 million, or $4.4 million net of tax, resulting from an amendment to the RLW member agreement to change the treatment of goodwill impairments for purposes of determining net income distributable to RLW's members. This is discussed further in Note 8.

Our gross margins have decreased to 6.9% in the Current Quarter from 9.3% in the Prior Quarter and from 9.0% for the three months ended June 30, 2012. Gross margins decreased to 6.6% in the Current Period from 9.3% in the Prior Period. Our gross margins continue to be adversely impacted by downward revisions to estimated profitability on certain projects.


The majority of our revenues and backlog is derived from fixed unit price contracts. Some of our revenues are derived from lump sum contracts. Fixed unit price contracts require us to provide materials and services at a fixed unit price based on approved quantities irrespective of our actual per unit costs. Lump sum contracts require that the total amount of work be performed for a single price irrespective of our actual costs. As discussed in "Item 1A. Risk Factors" in the 2011 Form 10-K, we realize a profit on our contracts only if we accurately estimate our costs and then successfully control actual costs and avoid cost overruns, and our revenues exceed actual costs. If our cost estimates for a contract are inaccurate, or if we do not execute the contract within our cost estimates, then cost overruns may cause the contract not to be as profitable as we expected or result in a loss, negatively affecting our cash flow, earnings and financial position.

In view of the significant revisions to estimated gross profits on contracts identified in the fourth quarter of 2011, management undertook a thorough review and determined that some of these revisions related to prior periods, but the impact of revising these estimates would not have had a material impact on revenues or gross profit reported in those prior periods had the changes been made in the appropriate period. Management also determined that the procedures performed by operating personnel to make periodic revisions in estimates, and the reviews of those estimates by operations management, were not adequate or timely enough in some instances to ensure that a material impact on the financial statements resulting from such revisions in estimates would be recognized in the proper period. Management determined that this deficiency in our internal controls was such that a material misstatement of our annual or interim financial statements would not have been prevented or detected on a timely basis and, therefore, this deficiency constituted a material weakness as of December 31, 2011. Based on certain of the revisions in estimates which were made in the Current Period and Quarter, management has determined that this material weakness continued to exist as of September 30, 2012.

While the risks of cost overruns and changes in estimated contract revenues are an inherent part of the construction business, management believes that there are internal changes that we can make in order to improve the profitability of our projects, reduce the variability in profitability of our projects in the future and strengthen the internal control environment. We are undertaking changes in the following areas:

changing roles and responsibilities to improve functional support and controls;

developing management tools designed to improve the estimating process and increase the oversight of that process;

implementing processes designed to better identify, evaluate and quantify risks for individual projects;

improving the methodologies for allocating overhead, indirect costs and equipment costs to individual projects; and

improving the timeliness and content of reporting available to operations management.

Although improvements have been made to the estimation process, there has not yet been an adequate period of time since the changes have been implemented to evaluate the effectiveness of these changes, and based on certain of the revisions in estimates which were made in the Current Period and Quarter, we have determined that the material weakness continues to exist as of September 30, 2012.

In addition to the factors discussed above which impact the profitability on individual projects, there are other factors which have adversely affected our ability to secure construction projects at favorable margins. Contracts for our highway and related bridge work are generally funded through federal and state authorizations. The federal government enacted the SAFETEA-LU bill in 2005, which authorized $244 billion for transportation spending through 2009. The SAFETEA-LU bill expired on September 30, 2009, and the federal government enacted a number of extensions on an interim basis, most recently through June 30, 2012. In July 2012, the federal government enacted the Moving Ahead for Progress in the 21st Century ("MAP-21") legislation, a two-year, $105 billion reauthorization of the federal surface transportation program. This legislation maintains annual federal highway funding close to the previous level of $41 billion under the SAFETEA-LU bill. While we believe that a longer term bill is needed, the new bill does alleviate some of the uncertainty which has adversely affected the levels of transportation and water infrastructure capital expenditures in our markets, reduced opportunities to replace backlog at reasonable margins and increased competition for new projects.


While we expect that implementation of the internal changes discussed above will improve profitability in the future, we do not expect to see a substantial impact on our 2012 results. In addition, we expect continued pressure on our gross margins on new contract awards. Projects in our backlog generally take 12 to 36 months to complete. Based on our current estimates, the gross margin in our backlog for 2012 is lower than the gross margin of 8.0% realized in 2011, partly as a result of the operational issues discussed above which resulted in the downward revisions of estimated gross profits on a number of construction projects and partly as a result of competitive bidding pressures when the contracts were added to backlog.

Revenues for the Current Period are 22% above the Prior Period as a result of the higher backlog at the end of 2011 as compared to 2010, the impact of a full period of operations for JBC and Myers, both of which were acquired in August 2011, and contract awards of $512 million from January 1, 2012 through September 30, 2012. However, as discussed above, based on estimated gross margins in our current backlog, we expect our overall gross margins for 2012 to be lower than the 8.0% reported for 2011. As discussed under "Results of Operations - Backlog at September 30, 2012" below, we have revised the definition of backlog to exclude low bids not officially awarded. Contract awards of $512 million include $125 million in awards previously reported in 2011 which we were the apparent low bidder on in 2011 but which were officially awarded in 2012 and excludes $79 million of contracts not officially awarded at September 30, 2012.

Our Markets

Demand for transportation and water infrastructure depends on a variety of factors, including overall population growth, economic expansion and the vitality of the market areas in which we operate, as well as unique local topographical, structural and environmental issues. In addition to these factors, demand for the replacement of infrastructure is driven by the general aging of infrastructure and the need for technical improvements to achieve more efficient or safer use of infrastructure and resources. Funding for this infrastructure depends on federal, state and local governmental resources, budgets and authorizations. Each of these factors is discussed more fully in "Item 1. Business-Our Markets" in the 2011 Form 10-K.

According to 2010 U.S. Census Bureau information, Texas, Utah, Nevada, Arizona and California each experienced significant population growth from 2005 to 2010 and over the long-term these states are expected to continue to experience population increases from 25.1 million, 2.8 million, 2.7 million, 6.4 million and 37 million people in 2010, respectively, to populations of over 33 million, 3 million, 4 million, 10 million and 46 million, respectively, by 2030.

The U.S. Department of Transportation ("U.S.DOT") had actual appropriations of $41.8 billion for federal highway financial assistance to the states for 2011, has authority to spend $41.5 billion in the fiscal year ending September 30, 2012, $39.7 billion in fiscal 2013 and $40.3 billion in fiscal 2014 for highways and bridges.

In January 2009, the 2030 Committee, appointed by the Texas Department of Transportation ("TxDOT") at the request of the Governor of the State of Texas, submitted its draft report of the transportation needs of Texas, which at that time had over 193,000 lane-miles and 50,000 bridges in its state highway system. The report stated that "With [the] population increase expected by 2030, transportation modes, costs and congestion are considered a possible roadblock to Texas's projected growth and prosperity." The report further indicated that Texas needs to spend approximately $315.0 billion (in 2008 dollars) for the period 2009 through 2030 to prevent worsening congestion and maintain economic competitiveness on its urban highways and roads, improve congestion/safety and partial connectivity on its rural highways, and to replace bridges.

In 2007, the voters of the State of Texas approved $5.0 billion of bonds for highway construction ("Prop 12 Bonds") to be repaid out of the State's general funds. The transportation construction expenditures for 2010 and 2011 were partially funded by $2.0 billion of proceeds from the Prop 12 Bonds, and the budget for the biennium 2012-2013 includes the remaining $3.0 billion of proceeds from the Prop 12 Bonds.

TxDOT contract awards ("lettings") for transportation construction projects are estimated to be $4.2 billion in 2012 and $4.1 billion in 2013, including a statewide and local portion of the Prop 12 Bonds discussed above.

In Texas, substantial funds for transportation infrastructure spending are also being provided by toll road and regional mobility authorities for construction of toll roads, which provides Sterling with additional construction contracting opportunities; however, such spending could be limited by federal, state and local funding limitations.

Spending for highway and bridge construction in Utah was $1.3 billion in 2011, and $700.9 million has been authorized for 2012. The details of the capital spending for 2013 have not been released; however the Utah Governor's recommendation for total capital spending in 2013 is approximately $911 million compared with $1.4 billion recommended for 2012.

Nevada's budget for construction of roadways and facilities is $377 million in 2012 and $369 million in 2013 compared with expenditures of between $300 million and $400 million in each of the 2010 and 2011 fiscal years.

Arizona's expenditures for transportation construction were $326 million in 2011, appropriations are $326 million in 2012 and a budget of $332 million has been requested for 2013.


California's transportation capital outlays and local assistance were $5.0 billion in 2011, while such expenditures are estimated to be $10.2 billion in 2012 and $6.2 billion in 2013. A substantial portion of the decrease between 2012 and 2013 is due to a reduction in expected Federal Trust highway funds.

Since 2008, the bidding environment in our markets has been much more competitive than in the past because of the following:

Reduced federal, state and local spending on transportation and water-related infrastructure.

Traditional competitors on larger transportation and water infrastructure projects appear to have been bidding at less than normal margins, sometimes at bid levels below our break-even pricing, in order to replenish their backlogs.

While our business includes only minimal residential and commercial infrastructure work, the severe fall-off in new projects in those markets has resulted in some residential and commercial infrastructure contractors bidding on smaller public sector transportation and water infrastructure projects, sometimes at bid levels below our break-even pricing, thus increasing competition and creating downward pressure on bid prices in our markets.

The entry of new competitors from other states.

These factors have limited our ability to replenish our backlog through successful bids for new projects and have compressed the profitability on many new projects where we submitted successful bids. While we have been more aggressive in bidding for some projects, we have not bid at prices where we anticipated we would incur loss margins in order to obtain new backlog. Nevertheless, in some instances we determined subsequent to the award that a job would most likely have a loss margin. Consistent with our policy, these losses are recorded when they become known.

Recent reductions in miles driven in the U.S. and more fuel efficient vehicles have reduced federal and state gasoline taxes and tolls collected. In addition, until the MAP-21 legislation enacted in July 2012, the federal government had been extending financial assistance to the states on an interim basis which negatively impacted the states' highway and bridge construction contracts awarded through the fiscal year 2012.

Further, the nationwide decline in home sales, the increase in foreclosures and the prolonged recession have resulted in decreases in property taxes and some other local taxes, which are among the sources of funding for municipal road, bridge and water infrastructure construction. Expenditures by municipalities may also be limited due to federal, state and local funding limitations in the current economic environment.

These and other factors have adversely affected the levels of transportation and water infrastructure capital awards and expenditures in our markets, reducing opportunities to replace backlog at reasonable margins and increasing competition for new projects. See "Recent Developments ? Financial Results for 2011, Operational Issues and Outlook for 2012 Financial Results" in the 2011 Form 10-K for further discussion of the impact on our financial results.

While we do expect that our markets will ultimately recover from the conditions described above and that our backlog and revenues will grow and gross margins, net income and earnings per share will return to levels more consistent with historical rates of return, we cannot predict the timing of such a return to historical normalcy in our markets. We believe that the Company is in sound financial condition and has the resources and management experience to weather current market conditions and to continue to compete successfully for projects as they become available at acceptable profit margin levels. See "Business-Markets," "Business-Our Customers" and "Business-Competition" in the 2011 Form 10-K for a more detailed discussion of our markets and their funding sources.

Results of Operations

Backlog at September 30, 2012

Backlog is our estimate of the revenues that we expect to earn in future periods on our construction projects. In prior periods we generally added the anticipated revenue value of each new project to our backlog when management reasonably determined that we would be awarded the contract and there were no known impediments to being awarded the contract. However, due to the operating environment of our California subsidiaries in which low bid awards are, at times, contested, management has revised the definition of backlog to exclude low bid awards not officially awarded. The new definition of backlog should be applied whenever backlog is mentioned throughout this document, and we have updated prior period backlog information to conform to our current definition. As the construction on our projects progresses, we also increase or decrease backlog to take into account our estimates of the effects of changes in estimated quantities, changed conditions, change orders and other variations from initially anticipated contract revenues, including completion penalties and incentives. During the Current Quarter, we were awarded $158 million in contracts, and at September 30, 2012, our backlog of $704 million excluded approximately $79 million of expected revenues for which the contracts had not yet been officially awarded.

Substantially all of the contracts in our contract backlog may be canceled at the election of the customer; however, we have not been materially adversely affected by contract cancellations or modifications in the past.


Results of Operations for the Current Quarter as Compared to the Prior Quarter and for the Current Period as compared to the Prior Period

                                             Three Months Ended                         Nine Months Ended
                                               September 30,                              September 30,
                                     2012          2011         % Change        2012          2011         % Change

Revenues                           $ 205,283     $ 159,427           28.8 %   $ 472,418     $ 387,167           22.0 %
Gross profit                       $  14,169     $  14,756           (4.0 )   $  31,202     $  35,937          (13.2 )
General and administrative
expenses, net                        (10,259 )      (7,071 )         45.1       (26,369 )     (19,427 )         35.7
Other operating income                   261            76             NM         3,017           226             NM
Operating income                       4,171         7,761          (46.3 )       7,850        16,736          (53.1 )
Gains (loss) on the sale of
securities and other                     617           212             NM         1,700           (33 )           NM
. . .
  Add STRL to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for STRL - All Recent SEC Filings
Copyright © 2014 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.