|
Quotes & Info
|
| CNL > SEC Filings for CNL > Form 10-Q on 30-Oct-2012 | All Recent SEC Filings |
30-Oct-2012
Quarterly Report
The following discussion and analysis should be read in combination with the
Registrants' Combined Annual Report on Form 10-K for the fiscal year ended
December 31, 2011, and Cleco and Cleco Power's Condensed Consolidated Financial
Statements contained in this Combined Quarterly Report on Form 10-Q. The
information included therein is essential to understanding the following
discussion and analysis. Below is information concerning the consolidated
results of operations of Cleco for the three and nine months ended September 30,
2012 and September 30, 2011.
RESULTS OF OPERATIONS
Overview
Cleco is a regional energy company that conducts substantially all of its
business operations through its two primary subsidiaries:
• Cleco Power, a regulated electric utility company, which owns 9 generating units with a total nameplate capacity of 2,524 MW and serves approximately 281,000 customers in Louisiana through its retail business and 10 communities across Louisiana and Mississippi through wholesale power contracts and
• Midstream, a wholesale energy business, which owns Evangeline (which operates Coughlin).
Cleco Power
Many factors affect Cleco Power's primary business of selling electricity. These
factors include the presence of a stable regulatory environment, which can
impact cost recovery and return on equity, as well as the recovery of costs
related to growing energy demand and rising fuel prices; the ability to increase
energy sales while containing costs; and the ability to meet increasingly
stringent regulatory and environmental standards. Key initiatives that Cleco
Power is currently working on include the Acadiana Load Pocket project, the AMI
project and long-term power supply options beyond 2012. These initiatives are
discussed below.
Acadiana Load Pocket Project
In September 2008, Cleco Power entered into an agreement with two other
utilities to upgrade and expand interconnected transmission systems in south
central Louisiana in an area known as the Acadiana Load Pocket. The project
received LPSC and SPP approval in February 2009. Cleco Power's estimated cost
for its portion of the project is $125.0 million, including AFUDC. As of
September 30, 2012, Cleco Power had spent $119.6 million on the project. A
return on and recovery of the costs associated with the completed portions of
the Acadiana Load Pocket project are included in base
revenue. The project was substantially completed by the end of June 2012. Remaining portions of the project are expected to be complete by December 2012. For information on the impact the Acadiana Load Pocket project is expected to have on base revenue, see "- Comparison of the Three Months Ended September 30, 2012 and 2011 - Cleco Power - Base."
AMI Project
In May 2010, Cleco Power accepted the terms of a $20.0 million grant from the
DOE under the DOE's small-grant process to implement advanced metering
technology for all of Cleco Power's retail customers. Cleco Power estimates the
project will cost $73.0 million, with the DOE grant providing $20.0 million
toward the project and Cleco Power providing the remaining $53.0 million. The
grant program is a part of the American Recovery and Reinvestment Act of 2009,
an economic stimulus package passed by Congress in February 2009. Advanced
metering technology includes the installation of electric meters that enable
two-way communication capabilities between a home or business and a utility
company. At September 30, 2012, Cleco Power had incurred $45.4 million in
project costs, of which $20.0 million has been submitted to the DOE for
reimbursement. As of September 30, 2012, Cleco Power had received $18.5 million
in payments from the DOE. The project is expected to be completed in the third
quarter of 2013. For more information on the AMI Project, see "- Financial
Condition - Regulatory and Other Matters - AMI Project."
Power Supply Options
Cleco Power is evaluating a range of long-term power supply options beyond 2012.
Cleco Power is continuing to update its IRP to look at future sources of supply
to meet its capacity and energy requirements and to comply with new
environmental standards. In August 2011, Cleco Power issued an RFP for resources
to enhance reliability for January through April 2012 and selected and
negotiated two agreements from the RFP, a power purchase agreement with NRG
Power Marketing LLC and a tolling agreement with Evangeline. Both agreements
began on January 1, 2012 and ended on April 30, 2012. In October 2011, a second
RFP, seeking up to approximately 750 MW of capacity and energy, for a three- or
five-year period was issued for supply starting May 1, 2012. Cleco Power
selected Evangeline's proposal for a 730-MW product beginning May 1, 2012, and
ending April 30, 2015. The definitive agreement between Evangeline and Cleco
Power was executed in January 2012 and approved by the LPSC in March 2012 and
FERC in April 2012. In May 2012, Cleco Power issued a draft RFP seeking
long-term resources beyond April 2015. The final RFP was issued in July 2012 and
proposals were received
from potential suppliers in August 2012. On October 30, 2012, Cleco Power announced Evangeline as the winning bidder in Cleco Power's 2012 Long-Term RFP. For more information on Cleco Power's RFPs, see "- Financial Condition - Regulatory and Other Matters - Generation RFP" and Item 1, "Notes to the Unaudited Condensed Consolidated Financial Statements - Note 15 - Subsequent Event."
Cleco Midstream
Evangeline
In March 2010, Evangeline restructured its tolling agreement with JPMVEC and
shortened the expiration of the prior long-term agreement from 2020 to December
31, 2011 (with a JPMVEC option to extend one year). JPMVEC did not exercise the
option to extend the tolling agreement and as a result, Coughlin's capacity and
energy became available to Midstream beginning January 1, 2012. Evangeline was
one of the successful bidders in Cleco Power's RFP for short-term 2012 resources
beginning January 1, 2012, and began providing 250 MW of capacity and energy to
Cleco Power under a tolling agreement through April 30, 2012. In addition to
Cleco Power's RFP referenced above, in December 2011, Evangeline was also
notified that Cleco Power selected its proposal to fulfill Cleco Power's
capacity and energy needs as defined in the Cleco Power RFP for contractual
resources beginning in 2012. The proposal was for a 730-MW product beginning May
1, 2012 and ending April 30, 2015. The definitive agreement between Evangeline
and Cleco Power was executed in January 2012 and was approved by the LPSC in
March 2012 and FERC in April 2012. Midstream has been marketing Coughlin's
capacity for periods beginning after April 30, 2015, and has been evaluating
various options to optimize Coughlin's value. On October 30, 2012, Cleco Power
announced that Evangeline was the winning bidder in Cleco Power's 2012 Long-Term
RFP. For more information, see "- Financial Condition - Regulatory and Other
Matters - Generation RFP" and Item 1, "Notes to the Unaudited Condensed
Consolidated Financial Statements - Note 15 - Subsequent Event."
Comparison of the Three Months Ended September 30, 2012 and 2011
|
|