|
Quotes & Info
|
| CNL > SEC Filings for CNL > Form 10-Q on 31-Jul-2012 | All Recent SEC Filings |
31-Jul-2012
Quarterly Report
The following discussion and analysis should be read in combination with the
Registrants' Combined Annual Report on Form 10-K for the fiscal year ended
December 31, 2011, and Cleco and Cleco Power's Condensed Consolidated Financial
Statements contained in this Combined Quarterly Report on Form 10-Q. The
information included therein is essential to understanding the following
discussion and analysis. Below is information concerning the consolidated
results of operations of Cleco for the three and six months ended June 30, 2012,
and June 30, 2011.
RESULTS OF OPERATIONS
Overview
Cleco is a regional energy company that conducts substantially all of its
business operations through its two primary subsidiaries:
• Cleco Power, a regulated electric utility company, which owns 9 generating units with a total nameplate capacity of 2,524 MW and serves approximately 281,000 customers in Louisiana through its retail business and 10 communities across Louisiana and Mississippi through wholesale power contracts; and
• Midstream, a wholesale energy business, which owns Evangeline (which operates Coughlin).
Cleco Power
Many factors affect Cleco Power's primary business of selling electricity. These
factors include the presence of a stable regulatory environment, which can
impact cost recovery and return on equity, as well as the recovery of costs
related to growing energy demand and rising fuel prices; the ability to increase
energy sales while containing costs; and the ability to meet increasingly
stringent regulatory and environmental standards. Key initiatives that Cleco
Power is currently working on include the Acadiana Load Pocket project, the AMI
project and long-term power supply options beyond 2012. These initiatives are
discussed below.
Acadiana Load Pocket Project
In September 2008, Cleco Power entered into an agreement with two other
utilities to upgrade and expand interconnected transmission systems in south
central Louisiana in an area known as the Acadiana Load Pocket. The project
received LPSC and SPP approval in February 2009. Cleco Power's estimated cost
for its portion of the project is $125.0 million, including AFUDC. As of
June 30, 2012, Cleco Power had spent $112.0 million on the project, including
AFUDC. A return on and recovery of the costs associated with the completed
portions of the Acadiana Load Pocket project are included in base revenue. The
project was substantially completed by the end of June 2012. Remaining portions
of the project are expected to be complete by December 2012. For information on
the impact the Acadiana Load Pocket project is expected to have on base revenue,
see "- Comparison of the Three Months Ended June 30, 2012, and 2011 - Cleco
Power - Base."
AMI Project
In May 2010, Cleco Power accepted the terms of a $20.0 million grant from the
DOE under the DOE's small-grant process to implement advanced metering
technology for all of Cleco Power's retail customers. Cleco Power estimates the
project will cost $73.0 million, with the DOE grant providing $20.0 million
toward the project and Cleco Power providing the remaining $53.0 million. The
grant program is a part of the American Recovery and Reinvestment Act of 2009,
an economic stimulus package passed by Congress in February 2009. Advanced
metering technology includes the installation of electric meters that enable
two-way communication capabilities between a home or business and a utility
company. At June 30, 2012, Cleco Power had incurred $24.7 million in project
costs, of which $10.6 million has been submitted to the DOE for reimbursement.
As of June 30, 2012, Cleco Power had received $8.1 million in payments from the
DOE. The project is expected to be completed in the third quarter of 2013. For
more information on the AMI Project, see "- Financial Condition - Regulatory and
Other Matters - AMI Project."
Power Supply Options
Cleco Power is evaluating a range of long-term power supply options beyond 2012.
Cleco Power is continuing to update its IRP to look at future sources of supply
to meet its capacity and energy requirements and to comply with new
environmental standards, primarily CSAPR. In August 2011, Cleco Power issued an
RFP for resources to enhance reliability for January through April 2012 and
selected and negotiated two agreements from the RFP, a power purchase agreement
with NRG Power Marketing LLC and a tolling agreement with Evangeline. Both
agreements began on January 1, 2012. In October 2011, a second RFP, seeking up
to approximately 750 MW of capacity and energy, for a three- or five-year period
was issued for supply starting May 1, 2012, to meet CSAPR. Cleco Power selected
Evangeline's proposal for a 730-MW product beginning May 1, 2012, and ending
April 30, 2015. The definitive agreement between Evangeline and Cleco Power was
executed in January 2012 and approved by the LPSC in March 2012 and FERC in
April 2012. In May 2012, Cleco Power issued a draft RFP seeking long-term
resources beyond April 2015. The final RFP was issued in July 2012. For more
information on Cleco Power's RFPs, see "- Financial Condition - Regulatory and
Other Matters - Generation RFP."
Cleco Midstream
Evangeline
In March 2010, Evangeline restructured its tolling agreement with JPMVEC and
shortened the expiration of the prior long-term agreement from 2020 to December
31, 2011 (with a JPMVEC option to extend one year). JPMVEC did not exercise the
option to extend the tolling agreement and as a result, Coughlin's capacity and
energy became available to Midstream beginning January 1, 2012. Evangeline was
one of the successful bidders in Cleco Power's RFP for short-term 2012 resources
beginning January 1, 2012, and began providing 250 MW of capacity and energy to
Cleco Power
under a tolling agreement through April 30, 2012. In addition to Cleco Power's RFP referenced above, in December 2011, Evangeline was also notified that Cleco Power selected its proposal to fulfill Cleco Power's capacity and energy needs as defined in the Cleco Power RFP for contractual resources to meet CSAPR beginning in 2012. The proposal was for a 730-MW product beginning May 1, 2012, and ending April 30, 2015. The definitive agreement between Evangeline and Cleco Power was executed in January 2012 and was approved by the LPSC in March 2012 and FERC in April 2012. Currently, Midstream is marketing Coughlin's capacity for periods beginning after April 30, 2015, and is evaluating various options to optimize Coughlin's value. For more information, see "- Financial Condition - Regulatory and Other Matters - Generation RFP."
Comparison of the Three Months Ended June 30, 2012, and 2011
|
|