Quarterly Report


MANAGEMENT'S FINANCIAL DISCUSSION AND ANALYSIS

Entergy operates primarily through two business segments: Utility and Non-Utility Nuclear.

· Utility generates, transmits, distributes, and sells electric power in service territories in four states that include portions of Arkansas, Mississippi, Texas, and Louisiana, including the City of New Orleans; and operates a small natural gas distribution business.

· Non-Utility Nuclear owns and operates six nuclear power plants located in the northern United States and sells the electric power produced by those plants primarily to wholesale customers. This business also provides services to other nuclear power plant owners.

In addition to its two primary, reportable, operating segments, Entergy also operates the non-nuclear wholesale assets business. The non-nuclear wholesale assets business sells to wholesale customers the electric power produced by power plants that it owns while it focuses on improving performance and exploring sales or restructuring opportunities for its power plants. Such opportunities are evaluated consistent with Entergy's market-based point-of-view.

Plan to Pursue Separation of Non-Utility Nuclear

See the Form 10-K for a discussion of the Board-approved plan to pursue a separation of the Non-Utility Nuclear business from Entergy through a tax-free spin-off of the Non-Utility Nuclear business to Entergy shareholders. Following are updates to that discussion.

Entergy Nuclear Operations, Inc., the current NRC-licensed operator of the Non-Utility Nuclear plants, filed an application in July 2007 with the NRC seeking indirect transfer of control of the operating licenses for the six Non-Utility Nuclear power plants, and supplemented that application in December 2007 to incorporate the planned business separation. The NRC approved Entergy Nuclear Operations, Inc.'s application on July 28, 2008, with the approval effective for a period of one year. In May 2009, Entergy Nuclear Operations, Inc. filed a request for extension of the approval for six months, through January 28, 2010, and the NRC approved the extension on July 24, 2009.

Pursuant to Federal Power Act section 203, in February 2008 an application was filed with the FERC requesting approval for the indirect disposition and transfer of control of jurisdictional facilities of a public utility. The FERC issued an order in June 2008 authorizing the requested indirect disposition and transfer of control. In August 2009 an amended application was filed with the FERC to reflect the transfer to the exchange trust by Entergy of the 19.9 percent of Enexus' common stock shares. In September 2009 the FERC approved the amended application.

As discussed more fully in the Form 10-K, on January 28, 2008, Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. requested approval from the Vermont Public Service Board (VPSB) for the indirect transfer of control, consent to pledge assets, issue guarantees and assign material contracts, amendment to certificate of public good, and replacement of guaranty and substitution of a credit support agreement for Vermont Yankee. Entergy Nuclear Operations, Inc. supplied supplemental data to the VPSB outlining the enhanced transaction structure detailed in the amended petition filed in New York (discussed below). On October 8, 2009, a memorandum of understanding was filed with the VPSB outlining an agreement reached with the Vermont Department of Public Service, which, if approved by the VPSB, would result in approval of the spin-off transaction in Vermont. A decision on the memorandum of understanding as submitted is pending before the VPSB. Entergy Nuclear Vermont Yankee requested that the VPSB expedite its final consideration and issue its decision and a final order approving the transactions by mid-November 2009.


Entergy Corporation and Subsidiaries
Management's Financial Discussion and Analysis

On July 13, 2009, Entergy Corporation, Entergy Nuclear FitzPatrick, LLC, Entergy Nuclear Indian Point 2, LLC, Entergy Nuclear Indian Point 3, LLC, Entergy Nuclear Operations, Inc., and Enexus filed a motion with the New York Public Service Commission (NYPSC) in connection with the planned separation requesting procedures and a schedule to enable the report of the presiding ALJs to be issued in time for the NYPSC to issue a final order no later than its regularly scheduled meeting in November 2009 so that the proposed reorganization can be completed by the end of 2009. In December 2008, notice had been provided to the NYPSC that the parties intended to conduct settlement discussions. The discussions did not produce an agreement and have ended. Nevertheless, Entergy endeavored to address and resolve the concerns of the trial staff of the NYPSC related to the financial strength of Enexus and has developed further enhancements to the reorganization proposal that it believes should resolve these concerns. Accordingly, in its July 2009 motion Entergy proposed to file an amended petition reflecting these enhancements for the NYPSC's consideration. In addition, in its motion Entergy sought to ensure that the scope of review by the NYPSC would remain confined to the three issues (i.e., operating capability, financial capability, and decommissioning funding) previously set forth by the NYPSC and further defined by the ALJs.

Five parties replied to the motion, generally in opposition to it. The ALJs issued a ruling on the motion on July 29, 2009. The ALJs declined to adopt a specific schedule and process, pending receipt of the amended petition and a reasonable opportunity for other interested parties to respond shortly thereafter. The ALJs stated that they were inclined to adopt a process with procedural milestones that mirror those previously employed in the proceeding, including but not limited to a reasonable opportunity for some follow-up discovery. The ALJs stated that they remain open to the possibility that evidentiary hearings might be held as a matter of discretion; however, nothing presented in the responses to the motion persuaded them that evidentiary hearings are inherently necessary. The ALJs declined to rule until after the amended petition is filed on whether the list of issues in their previous ruling should be expanded or modified.

On August 11, 2009, Enexus filed with the NYPSC an amended petition for an order approving the reorganization and associated debt financings. The amended petition describes proposed enhancements to the corporate reorganization. These proposed enhancements include a commitment to reserve at least $350 million of liquidity, a $1.0 billion reduction in long-term bonds to $3.5 billion, and an increase in the initial cash balance left at Enexus to $750 million from the original $250 million. The amended petition requested that the NYPSC: issue an order approving the corporate reorganization and associated financings; confirm the corporate reorganization will have no impact on the Enexus companies' status as lightly regulated entities; and issue a negative declaration and undertake no further review under the New York State Environmental Quality Review Act. On August 11, 2009, Enexus also served updated discovery responses on the other parties in this proceeding.

Once the spin-off transaction is complete, Entergy Corporation's shareholders will own all Entergy common stock and will receive a distribution of 80.1 percent of the Enexus common shares. Entergy will transfer the remaining Enexus common shares to a trust. While held by the trust, the Enexus common shares will be voted by the trustee in the same proportion as the other Enexus common shares on any matter submitted to a vote of the Enexus shareholders. Within a period of up to 18 months after the spin-off, Entergy is expected to exchange the Enexus common shares retained in the trust for Entergy common shares. Enexus common shares not ultimately exchanged, if any, will be distributed to Entergy shareholders.

On August 21, 2009, the ALJs issued a Ruling Concerning Scope, Process, and Schedule that determined that additional record development was warranted in light of the changes contained in the amended petition. The August 21, 2009 ruling limited the issues requiring further record development to environmental significance under the New York State Environmental Quality Review Act and whether Enexus will be at least as capable as Entergy in meeting all financial and other obligations related to the ownership and operation of the New York nuclear facilities. To facilitate further development of the record, the ruling further established an interim schedule that provided for: (1) the prompt scheduling of a conference; (2) a discovery period to be completed by September 30, 2009; and (3) separate rounds of comments on State Environmental Quality Review Act and substantive issues to be completed by November 12, 2009. The ALJs invited comment on the ruling on or before August 28, 2009. On September 4, 2009, the ALJs issued a further ruling revising the


Entergy Corporation and Subsidiaries Management's Financial Discussion and Analysis

schedule adopted on an interim basis on August 21, 2009 to provide for simultaneous briefing of State Environmental Quality Review Act and substantive issues. The September 4, 2009 ruling left until after the technical conference further possible revisions to the procedural schedule. On September 11, 2009, a technical conference was held at the offices of the NYPSC. Following the technical conference, the ALJs indicated that further discovery with respect to the changes reflected in the amended petition was warranted. On September 16, 2009, the ALJs issued a Further Ruling Concerning Scope, Process, and Schedule that established: (1) a discovery period to be completed by October 15, 2009; and (2) a comment period requiring open issues to be fully briefed by November 12, 2009. In early November 2009 the New York State Attorney General's Office, the New York Department of Public Service's Staff, and Westchester County filed initial comments on the amended petition stating their opposition to Enexus' request in the amended petition.

On October 1, 2009, Enexus executed Amendment No. 1 to its credit agreement dated December 23, 2008, increasing the total credit facility amount to $1.2 billion from $1.175 billion. Enexus is not permitted to draw down the facility until certain customary and transactional conditions related to the spin-off are met on or prior to July 1, 2010.

Hurricane Gustav and Hurricane Ike

See the Form 10-K for a discussion of Hurricane Gustav and Hurricane Ike, which caused catastrophic damage to portions of Entergy's service territories in Louisiana and Texas, and to a lesser extent in Arkansas and Mississippi, in September 2008. In April 2009 a law was enacted in Texas that authorizes recovery of these types of costs by securitization. Entergy Texas filed its storm cost recovery case with the PUCT in April 2009 seeking a determination that $577.5 million of Hurricane Ike and Hurricane Gustav restoration costs are recoverable, including estimated costs for work to be completed. On August 5, 2009, Entergy Texas submitted to the ALJ an unopposed settlement agreement to resolve all issues in the storm cost recovery case. Under the terms of the agreement $566.4 million, plus carrying costs, are eligible for recovery. Insurance proceeds will be credited as an offset to the securitized amount. The PUCT approved the settlement in August 2009, and in September 2009 the PUCT approved recovery of the costs, plus carrying costs, by securitization.

In the third quarter 2009, Entergy settled with its insurer on its Hurricane Ike claim and Entergy Texas received $75.5 million in proceeds (Entergy received a total of $76.5 million).

In November 2009, Entergy Texas Restoration Funding, LLC (Entergy Texas Restoration Funding), a company wholly-owned and consolidated by Entergy Texas, issued $545.9 million of senior secured transition bonds (securitization bonds). With the proceeds, Entergy Texas Restoration Funding purchased from Entergy Texas the transition property, which is the right to recover from customers through a transition charge amounts sufficient to service the securitization bonds. Entergy Texas expects to use the proceeds to reduce debt. See Note 4 to the financial statements for additional information regarding the securitization bonds.

Entergy Gulf States Louisiana and Entergy Louisiana filed their storm cost recovery case with the LPSC in May 2009. Entergy Gulf States Louisiana seeks a determination that $152.6 million of storm restoration costs are recoverable and seeks to replenish its storm reserve in the amount of $90 million. Entergy Louisiana seeks a determination that $267.4 million of storm restoration costs are recoverable and seeks to replenish its storm reserve in the amount of $200 million. The storm restoration costs are net of costs that have already been paid from previously funded storm reserves. In September 2009, Entergy Gulf States Louisiana and Entergy Louisiana made a supplemental filing to, among other things, recommend recovery of the costs and replenishment of the storm reserves by Louisiana Act 55 (passed in 2007) financing. Entergy Gulf States Louisiana and Entergy Louisiana recovered their costs from Hurricane Katrina and Hurricane Rita primarily by Act 55 financing. The parties have agreed to a procedural schedule that includes March 2010 hearing dates for both the recoverability and the method of recovery proceedings.

Entergy Arkansas January 2009 Ice Storm

See the Form 10-K for a discussion of the severe ice storm that caused significant damage to Entergy Arkansas' transmission and distribution lines, equipment, poles, and other facilities in January 2009. See Note 2 to the financial statements herein for a discussion of Entergy Arkansas' accounting for and recovery of these storm costs.


  Add ETR to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for ETR - All Recent SEC Filings
Sign Up for a Free Trial to the NEW EDGAR Online Pro
Detailed SEC, Financial, Ownership and Offering Data on over 12,000 U.S. Public Companies.
Actionable and easy-to-use with searching, alerting, downloading and more.
Request a Trial      Sign Up Now


Copyright © 2009 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.