The following plan of operation should be read in conjunction with our financial statements and the notes thereto included elsewhere in this report. Statements contained herein which are not historical facts are forward-looking statements, as that term is defined by the Private Securities Litigation Reform Act of 1995, including statements relating to our plans, objectives, expectations and intentions. Although we believe that the expectations reflected in such forward-looking statements are reasonable, forward-looking statements are subject to risks and uncertainties that could cause actual results to differ from those projected. We caution investors that any forward-looking statements made by us are not guarantees of future performance and that actual results may differ materially from those in the forward-looking statements. Such risks and uncertainties include, without limitation: established competitors who have substantially greater financial resources and operating histories, regulatory delays or denials, ability to compete as a start-up company in a highly competitive market, and access to sources of capital.
Results of Operations
We have conducted no material operations during the year ended March 31, 2009, and do not have any present operations. During the year ended March 31, 2009, we generated no revenues. Accordingly, a discussion of our results of operations is not meaningful and will not be presented herein.
The following table provides selected financial data about our company as of and for the year ended March 31, 2009, and as of July 31, 2008
Balance Sheet Data: March 31, 2009 July 31, 2008
Cash $ 21,770 $ 101
Total assets $ 22,150 $ -
Total liabilities $ 1,500 $ -
Stockholders' equity $ 20,650 $ 101
|
Liquidity and Capital Resources
The report of our auditors on our audited financial statements for the fiscal year ended March 31, 2009, contains a going concern qualification as we have suffered losses since our inception. We have minimal assets and have achieved no operative revenues since our inception. We have depended on loans and sales of equity securities to conduct operations. Unless and until we commence material operations and achieve material revenues, we will remain dependent on financings to continue our operations. Because of our limited cash on hand, we will be required to raise additional capital over the next twelve months to meet our ongoing expenses.
The following discussion provides information that we believe is relevant to an assessment and understanding of the results of operations and financial condition of our company. It should be read in conjunction with the Financial Statements and accompanying Notes.
Plan of Operation
Our plan of operation is divided into four phases, as follows: (I) retain, on a
consulting basis, engineers to conduct technical and economic feasibility
studies of sites for construction of the first energy tower power plant, (II)
negotiate and enter into a power purchase agreement with a utility company,
(III) retain, on a consulting basis, engineers to design the first energy tower
power plant and request for proposals from subcontractors and equipment
manufacturers for the construction of the first energy tower power plant, and
(IV) construct a full-scale energy towers power plant. We have begun discussions
with an engineering firm to engage in technical and economic feasibility studies
but have not yet commenced any other operations or activities.
Our plan of operation for the following twelve months is to (i) complete Phase I of our program, which is to conduct technical and economic feasibility studies of sites for construction of the first energy tower power plant, and (ii) begin Phase II of our program, which is to negotiate and enter into a power purchase agreement with a utility company (with the final power purchase agreement to be executed in March 2010). In addition to the $8,500,000 we anticipate spending for Phase I and II for the development program as outlined below, we anticipate spending an additional $60,000 on professional and administrative fees, complying with reporting obligations and arranging financing for Phase I and II of our development program. Total expenditures over the next 12 months are therefore expected to be approximately $6,560,000, $60,000 of which is the amount to be raised in this offering. If we experience a shortage of funds prior to funding during the next 12 months, we may utilize funds from Robert O'Leary, our Chairman of the Board of Directors, who has informally agreed to advance funds to allow us to pay for professional fees, including fees payable in connection with the filing of this registration statement and operation expenses, however he has no formal commitment, arrangement or legal obligation to advance or loan funds to the company. We will require the funds from this offering to proceed.
If we are successful in raising funds from an offering of common stock for proceeds of $60,000, we plan to commence activities to raise the $6,000,000 funds required for Phase I of the development program in the winter of 2009/2010. We expect this phase to take 30-90 days to complete and an additional 9 to 11 months for engineers to conduct technical and economic feasibility studies of sites for construction of the first energy tower power plant. We cannot provide investors with any assurance that we will be able to raise sufficient funds to proceed with any work or activities on Phase I of the development program. We plan to raise the additional funding for Phase I by way of a private debt or equity financing. We have commenced activities to raise such funds, raising $26,080 in November and December 2008, and continue to attempt to raise funds.
The above program costs are management's estimates and the actual project costs may exceed our estimates. To date, we have not commenced with any activities or operations of any phase of our development program.
Following Phase I of the development program, if it proves successful, in that engineers successfully conduct technical and economic feasibility studies of sites for construction of the first energy tower power plant, we intend to, subject to financing, proceed with Phase II of our development program, Phase II is to negotiate and enter into a power purchase agreement with a utility company. The estimated cost of Phase II is $2,500,000 and is anticipated take approximately 7 months to complete. As with Phase I, we cannot provide investors with any assurance that we will be able to raise sufficient funds to proceed with any work or activities on Phase II of our development program. We plan to raise the additional funding for Phase II by way of a private debt or equity financing, but have not commenced any activities to raise such funds.
Following Phase II of the development program, if it proves successful, in that we successfully negotiate and enter into a power purchase agreement with a utility company, we intend to proceed with Phase III of our development program if we are able to raise the funds necessary. Phase III is to make the final design of the first energy tower power plant and request proposals from subcontractors and equipment manufacturers for the construction of the first energy tower power plant. The estimated cost of Phase III is $6,500,000 and is estimated to take approximately 6 months to complete. As with Phases I and II, we cannot provide investors with any assurance that we will be able to raise sufficient funds to proceed with any work or activities on Phase III of the development program, and we have no current plans on how to raise the additional funding.
We anticipate commencing Phase II of our development program in March 2010, depending on whether Phase I program proves successful in establishing the technical and economic feasibility studies of sites for construction of the first energy tower power plant. Subject to financing, we anticipate commencing Phase III of our development program in 2010, depending on whether Phase II program proves successful in negotiating and entering into a power purchase agreement with a utility company. As with Phases I and II, we will require additional funding to proceed with Phase III, we have no current plans on how to raise the additional funding, though we believe that if we must first successfully negotiate and enter into a power purchase agreement with a utility company, as planned for Phase III, in order to successfully commence financing activities for Phase IV, which is the construction of the first full-scale energy towers power plant.
We estimate Phase IV to take 2 to 4 years to complete, subject to financing, and to cost between $300,000,000 and $1.5 billion to complete. As with Phases I, II, and III, we will require additional funding to proceed with Phase IV, we have no current plans on how to raise the additional funding.
Off -balance Sheet Arrangements
We do not have any off-balance sheet arrangements that have or are reasonably likely to have a current or future effect on our financial condition, changes in financial condition, revenues or expenses, results of operations, liquidity, capital expenditures or capital resources that is material to investors.
|