Quotes & Info
|
| MAM > SEC Filings for MAM > Form 8-K on 22-Jan-2009 | All Recent SEC Filings |
22-Jan-2009
Other Events
On January 21, 2009, in deliberations of the Maine Public Utilities Commission (MPUC), the Commission voted to dismiss without prejudice the petition of Maine Public Service Company and Central Maine Power Company to build a transmission line connecting northern Maine to the New England transmission grid, originally filed in Docket No. 2008-256. As described in a press release filed in a Form 8-K dated January 16, 2009, the parties intend to continue to pursue development of a transmission line to enable development of wind generation projects and potentially to connect northern Maine to the New England electric grid. A written order from the MPUC is expected shortly; this filing will not be updated unless there is any material new information in the order.
|
|