On December 31, 2008, Aventine Renewable Energy - Aurora West, LLC, a
wholly-owned indirect subsidiary of Aventine Renewable Energy Holdings, Inc.
(hereinafter together called "Aventine") and Kiewit Energy Company ("Kiewit")
entered into a change order to the Engineering, Procurement and Construction
Services Fixed Price Contract (the "EPC Contract") for the ethanol facility
currently under construction in Aurora, Nebraska.
The change order suspends construction of the ethanol facility for up to 180 days and addresses the extension of the construction schedule in the event of resumption of work. The payment schedule under the agreement was adjusted through June 30, 2009 as a result of this suspension of construction. Aventine also agreed to pay Kiewit and its subcontractors approximately $4.9 million in suspension costs. The change order further provides for suspension services, the resumption of work, and the tolling of deadlines and milestones during the suspension, cancels a letter of credit granted in favor of Aventine, provides for Kiewit's forbearance of remedies, and provides for various other responsibilities and obligations of the parties common to such construction contracts and their suspension.
The change order terminates the parties' amendment to the EPC Contract entered into on October 1, 2008.
(a) Financial statements of businesses acquired - Not Applicable