Form 10-Q for ORMAT TECHNOLOGIES, INC.


6-Nov-2008

Quarterly Report


ITEM 2. MANAGEMENT'S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS

This quarterly report on Form 10-Q includes "forward-looking statements" within the meaning of the Private Securities Litigation Reform Act of 1995. All statements, other than statements of historical facts, included in this quarterly report that address activities, events or developments that we expect or anticipate will or may occur in the future, including such matters as our projections of annual revenues, expenses and debt service coverage with respect to our debt securities, future capital expenditures, business strategy, competitive strengths, goals, development or operation of generation assets, market and industry developments and the growth of our business and operations, are forward-looking statements. When used in this quarterly report on Form 10-Q, the words "may", "will", "could", "should", "expects", "plans", "anticipates", "believes", "estimates", "predicts", "projects", "potential", or "contemplate" or the negative of these terms or other comparable terminology are intended to identify forward-looking statements, although not all forward-looking statements contain such words or expressions. The forward-looking statements in this quarterly report are primarily located in the material set forth under the headings "Management's Discussion and Analysis of Financial Condition and Results of Operations", "Risk Factors", and "Notes to Condensed Consolidated Financial Statements", but are found in other locations as well. These forward-looking statements generally relate to our plans, objectives and expectations for future operations and are based upon management's current estimates and projections of future results or trends. Although we believe that our plans and objectives reflected in or suggested by these forward-looking statements are reasonable, we may not achieve these plans or objectives. You should read this quarterly report on Form 10-Q completely and with the understanding that actual future results and developments may be materially different from what we expect due to a number of risks and uncertainties, many of which are beyond our control. We will not update forward-looking statements even though our situation may change in the future.

Specific factors that might cause actual results to differ from our expectations include, but are not limited to:

• significant considerations, risks and uncertainties discussed in this quarterly report;

• operating risks, including equipment failures and the amounts and timing of revenues and expenses;

• geothermal resource risk (such as the heat content of the reservoir, useful life and geological formation);

• environmental constraints on operations and environmental liabilities arising out of past or present operations, including the risk that we may not have, and in the future may be unable to procure, any necessary permits or other environmental authorization;

• construction or other project delays or cancellations;

• financial market conditions and the results of financing efforts;

• political, legal, regulatory, governmental, administrative and economic conditions and developments in the United States and other countries in which we operate;

• the enforceability of the long-term power purchase agreements for our projects;

• contract counterparty risk;

• weather and other natural phenomena;

• the impact of recent and future federal and state regulatory proceedings and changes, including legislative and regulatory initiatives regarding deregulation and restructuring of the electric utility industry and incentives for the production of renewable energy in the United States and elsewhere;

• changes in environmental and other laws and regulations to which our company is subject, as well as changes in the application of existing laws and regulations;

• current and future litigation;


Table of Contents

• our ability to successfully identify, integrate and complete acquisitions;

• competition from other similar geothermal energy projects, including any such new geothermal energy projects developed in the future, and from alternative electricity producing technologies;

• the effect of and changes in economic conditions in the areas in which we operate;

• market or business conditions and fluctuations in demand for energy or capacity in the markets in which we operate;

• the direct or indirect impact on our company's business resulting from terrorist incidents or responses to such incidents, including the effect on the availability of and premiums on insurance;

• the effect of and changes in current and future land use and zoning regulations, residential, commercial and industrial development and urbanization in the areas in which we operate;

• the risk factors set forth in our annual report on Form 10-K for the year ended December 31, 2007 and any updates contained herein which may have a significant impact on our business, operating results or financial condition;

• other uncertainties which are difficult to predict or beyond our control and the risk that we incorrectly analyze these risks and forces or that the strategies we develop to address them could be unsuccessful; and

• other risks and uncertainties detailed from time to time in our filings with the Securities and Exchange Commission (SEC).

Investors are cautioned that these forward-looking statements are inherently uncertain. Should one or more of these risks or uncertainties materialize, or should underlying assumptions prove incorrect, actual results or outcomes may vary materially from those described herein. We undertake no obligation to update forward-looking statements even though our situation may change in the future. Given these risks and uncertainties, readers are cautioned not to place undue reliance on such forward-looking statements.

The following discussion and analysis of our financial condition and results of operations should be read together with our condensed consolidated financial statements and related notes included elsewhere in this report and the "Risk Factors" section of our annual report on Form 10-K for the year ended December 31, 2007 and any updates contained herein as well as those set forth in our reports and other filings made with the SEC.

General

Overview

We are a leading vertically integrated company engaged in the geothermal and recovered energy power business. We design, develop, build, own and operate clean, environmentally friendly geothermal and recovered energy-based power plants using equipment that we design and manufacture.

Our geothermal power plants include both power plants that we have built and power plants that we have acquired, while all of our recovered energy-based plants have been constructed by us. We conduct our business activities in two business segments, which we refer to as our Electricity Segment and Products Segment. In our Electricity Segment, we develop, build, own and operate geothermal and recovered energy-based power plants in the United States and geothermal power plants in other countries around the world and sell the electricity they generate. In our Products Segment, we design, manufacture and sell equipment for geothermal and recovered energy-based electricity generation, remote power units and other power generating units and provide services relating to the engineering, procurement, construction, operation and maintenance of geothermal and recovered energy power plants. Both our Electricity Segment and Products Segment operations are conducted in the United States and throughout the world. We currently own or control, as well as operate, geothermal projects in the United States, Guatemala, Kenya Nicaragua and New Zealand, as well as recovered energy generation (REG) plants in the United States. During the nine months ended September 30, 2008 and 2007, our U.S. power plants generated 1,620,596 MWh and 1,461,153 MWh, respectively.


Table of Contents

For the nine months ended September 30, 2008, our Electricity Segment represented approximately 76.3% of our total revenues, while our Products Segment represented approximately 23.7% of our total revenues during such period.

During the nine months ended September 30, 2008, our total revenues increased by 10.7% (from $225.3 million to $249.3 million) over the same period last year. Revenues from the Electricity Segment increased by 18.5%, while revenues from the Products Segment decreased by 8.7%.

For the nine months ended September 30, 2008, total Electricity Segment revenues from the sale of electricity by our consolidated power plants were $190.1 million. In addition, revenues from our 50% ownership of the Mammoth project for the nine months ended September 30, 2008 were $7.3 million. This additional data is a Non-Generally Accepted Accounting Principles (Non-GAAP) financial measure, as defined by the SEC. There is no comparable GAAP measure. Management believes that such Non-GAAP data is useful to the readers as it provides a more complete view of the scope of activities of the power plants that we operate. Our investment in the Mammoth project is accounted for in our consolidated financial statements under the equity method and the revenues are not included in our consolidated revenues for the nine months ended September 30, 2008.

During the nine months ended September 30, 2008, revenues attributable to our Products Segment were $59.2 million, as compared to $64.8 million during the nine months ended September 30, 2007.

From the beginning of the year, we received purchase orders for the supply and construction of geothermal and REG plants in a total amount of $179 million. Of this amount, approximately $19 million is subject to a notice to proceed, which we expect to receive in the near future.

REG continues to present opportunities for us in the United States and throughout the world. During the nine months ended September 30, 2008, we recognized revenues in our Products Segment of approximately $11.1 million from REG compared to $28.4 million during the nine months ended September 30, 2007.

Revenues from our Electricity Segment are relatively predictable, as they are derived from sales of electricity generated by our power plants pursuant to long-term power purchase agreements. The price for electricity under all but one of our power purchase agreements is effectively a fixed price at least through May 2012. The power purchase agreement of the Puna project has a variable energy rate based on the local utility's short run avoided costs, which are the incremental costs that the power purchaser avoids by not having to generate such electrical energy itself or purchase it from others. In the nine months ended September 30, 2008, 78.6% of our electricity revenues were derived from contracts with fixed energy rates, and therefore most of our electricity revenues were not affected by the fluctuations in energy commodity prices. However, electricity revenues are subject to seasonal variations and can be affected by higher-than-average ambient temperatures, as described below under the heading "Seasonality". Revenues attributable to our Products Segment are based on the sale of equipment and the provision of various services to our customers. These revenues may vary from period to period because of the timing of our receipt of purchase orders and the progress of our execution of each project.

Our management assesses the performance of our two segments of operation differently. In the case of our Electricity Segment, when making decisions about potential acquisitions or the development of new projects, we typically focus on the internal rate of return of the relevant investment, relevant technical and geological matters and other relevant business considerations. We evaluate our operating projects based on revenues and expenses, and our projects that are under development based on costs attributable to each such project. By contrast, we evaluate the performance of our Products Segment based on the timely delivery of our products, performance quality of our products and costs actually incurred to complete customer orders as compared to the costs originally budgeted for such orders.

Recent Developments

• On October 29, 2008, our subsidiary, Ormat Funding Corp. (OFC), successfully consummated a consent solicitation, which was launched on October 16, 2008, relating to OFC's 8.25% Senior Secured Notes due 2020. The consent solicitation grants OFC approval: (i) to replace an aging power plant at the


Table of Contents

Mammoth project with a new larger plant, and/or to construct a new plant while maintaining the existing power plants at the Mammoth project;
(ii) for possible construction and installation of solar power generation equipment to enhance the Brady and Ormesa projects; and (iii) to enter into an equity transaction whereby OFC's parent, Ormat Nevada Inc. (Ormat Nevada), will sell a portion of its equity interest in OFC to an institutional investor that is able to utilize certain income tax benefits.

• In October 2008, together with the U.S. Department of Energy, we started the testing phase of a geothermal power project at a producing oil well. The project, which was conducted at the Oil Test Center near Caspar, WY uses Ormat Organic Rankine Cycle (ORC) power generation system and provides fuel-free power that is intended to increase productivity and extend the longevity of oil wells. We are now assessing the feasibility of utilizing these wells to support on site generation by employing Ormat's factory integrated sub-megawatt geothermal power units, based on our proprietary ORC technology.

• In the third quarter of 2008, we completed the construction of an 8.3MW power plant located in Kawerau, New Zealand. We have a 49% ownership interest in the project and we have an option to acquire the remaining 51% at a nominal value. We intend to exercise this option before the end of 2008.

• In the third quarter of 2008, we received from ENAGAS, S.A. of Madrid, Spain, a notice to proceed with the construction of one OEC unit for a REG plant specially designed to use the residual energy from the vaporization process at a liquefied natural gas regasification terminal located in Huelva, Spain.

• In October 2008, we successfully completed the Steamboat 2/3 upgrade project. The upgrade included the replacement of the four Rotoflow turbines originally installed at these plants with direct drive gearless 11 MW axial turbines, each designed and manufactured by us specifically for geothermal use. With the completion of this project and the installation of field-proven turbines, we believe that there will be significant improvement in both the performance and availability of these two plants, which have been experiencing high maintenance costs and low run time of the replaced turbines.

• On September 17, 2008, we filed a universal shelf registration statement on Form S-3, which was declared effective by the SEC on October 2, 2008. The shelf registration statement replaces our former shelf registration statement, which would have expired in January 2009, and provides us with the opportunity to issue various types of securities, including debt securities, common stock, warrants and units of our company, from time to time for a period of three years, in one or more offerings up to a total dollar amount of $1.5 billion. Pursuant to the shelf registration statement, we may periodically offer one or more of the registered securities in amounts, at prices, and on terms to be announced when, and if, the securities are offered. At the time any offering is made under the shelf registration statement, the offering specifics will be set out in a prospectus supplement.

• In September 2008, we secured geothermal rights for approximately 35,000 acres of land to explore geothermal resources in the vicinity of Anchorage, Alaska's largest city. We won 15 of the 16 tracts offered for lease on Mount Spurr, a snowcapped 11,070-foot volcano, 75 miles west of Anchorage.

• In July 2008, we secured three new lease agreements covering approximately 20,000 acres of federal land in Nevada and California.

• In July 2008, the Public Utilities Commission of Nevada (PUCN) approved a Joint Ownership Agreement (JOA) with Nevada Power Company, a subsidiary of Sierra Pacific Resources, and an amendment to the existing power purchase agreement. The JOA was signed in March 2008 for the Carson Lake geothermal project located in Churchill County, Nevada, that is currently under development by us. We will develop the project on our own until the resource is sufficiently defined at a level that is capable of supporting at least 30 MW and Nevada Power Company has received regulatory approval to acquire its 50 percent ownership interest. Following Nevada Power Company's acquisition of its 50 percent interest, we will continue to develop the project on behalf of the owners. If the development results in a resource that cannot support at least 30 MW, the parties are not obligated to close the acquisition and we may continue to develop the project by ourselves. Under the JOA each


Table of Contents

party will own a 50 percent undivided interest in the project as tenants-in-common. To acquire its project interest, Nevada Power Company will pay 50 percent of the costs expended to the closing date of the acquisition plus a fee. Drilling, construction, and operating and maintenance (O&M) costs going forward will be governed by the JOA and separate Drilling Services, EPC and O&M agreements.

• In July 2008, PT Perusahaan Listrik Negara, the state owned Indonesian power company, accepted the entry of Kyushu Electric to the Sarulla consortium, which currently is comprised of a wholly owned subsidiary of ours, a subsidiary of Medco Energi Internasional Tbk, Itochu Corporation of Japan and Kyushu Electric. The entry of Kyushu Electric reduced our ownership interest in the consortium to 12.75%.

• In June 2008, two of our subsidiaries entered into an Engineering, Procurement and Construction (EPC) contract with Contact Energy Ltd. of New Zealand for the construction of the Centennial Binary Plant, a new geothermal plant to be constructed in the Tauhara Geothermal field in New Zealand. The contract's value is approximately $42.0 million and construction of the power plant is expected to be completed within 23 months from the contract date. Contact Energy Ltd. is New Zealand's largest geothermal power plant owner and operator, as well as the country's largest wholesaler and retailer of natural gas and liquid petroleum gas.

• In June 2008, we entered into a supply contract with MEGE - Menderes Geothermal Elektrik Uretim, A.S. for the supply of equipment for a new geothermal power plant to be constructed in Turkey. The contract's value is approximately $16.0 million and delivery is expected to be completed within 16 months from the contract date.

• On May 14, 2008, we completed a sale of 3,100,000 shares of common stock to Lehman Brothers Inc. in a block trade at a price of $48.36 per share (net of underwriting fees and commissions), under our shelf registration statement filed in early 2006. Net proceeds to us, after deducting underwriting fees and commissions and estimated offering expenses associated with the offering, were approximately $149.7 million.

• In April 2008, we entered into an EPC contract with Montana-Dakota Utilities Co. for a 5.3 MW REG power plant to be located on the Northern Border Pipeline compressor station in Morton County, North Dakota. Subject to regulatory approvals, the project is scheduled to be completed in the fourth quarter of 2009.

• In April 2008, we commenced commercial operation of the Heber South geothermal project located in the Imperial Valley, California.

• In April 2008, our wholly owned subsidiary, Ormat Nevada, concluded the second closing under a 2007 transaction to monetize production tax credits and other favorable tax attributes, such as accelerated depreciation, generated from certain of its geothermal power projects. The first closing of the transaction occurred on June 7, 2007. Pursuant to the transaction, affiliates of Morgan Stanley & Co. Incorporated and Lehman Brothers Inc. (which has since been acquired by Barclays) became institutional equity investors in a newly formed subsidiary of Ormat Nevada, OPC LLC (OPC). Under this second closing, Ormat Nevada transferred the Galena 3 geothermal project to OPC, and received from the institutional equity investors $63.0 million, net of transaction costs. As operator of all of the projects in the OPC portfolio, Ormat Nevada will continue to operate and maintain the Galena 3 project.

• In March 2008, we signed a new 20-year power purchase agreement with Great River Energy, a Minnesota Cooperative Corporation of Elk River, Minnesota, for the sale of electricity generated from a 5.3 MW Ormat REG facility to be constructed at a compressor station along the Northern Border natural gas pipeline. The new facility will convert the recovered waste heat from the exhaust of an existing gas turbine into electricity. We have already secured the rights to the waste heat for the new facility. We expect the plant to be commissioned in 2009 or early 2010.


Table of Contents

• In March 2008, we entered into an EPC contract with Nevada Geothermal Power (NGP) for the supply and construction of a 49.5 MW power plant, consisting of three Ormat Energy Converters units, which are guaranteed to produce
16.5 MW (gross) each, at NGP's Blue Mountain geothermal project in Nevada. The total EPC contract value is $76 million and the project is scheduled to be completed in the fourth quarter of 2009.

• In March 2008, we entered into an EPC contract with Nevada Power Company for a 6 MW REG power plant in the Goodsprings area, approximately 35 miles south of Las Vegas, Nevada. The project is subject to a notice to proceed and is scheduled to be completed in 2010.

• In March 2008, the California Public Utilities Commission approved a new 20-year power purchase agreement that we entered into in June 2007 with Southern California Edison Company (Southern California Edison) for the sale of 50 MW of energy to be produced from the North Brawley project, which we are currently constructing in Imperial County, California. The power purchase agreement includes an option to increase the capacity of the plant and the amount of energy to be sold up to 100 MW at our discretion.

• In March 2008, the PUCN approved the agreement we reached in May 2007 with Sierra Pacific Power Company and Nevada Power Company, the purchasers of electricity generated by our existing and planned geothermal power projects in Nevada, regarding certain amendments to the power purchase agreements for a number of our existing geothermal projects in operation and some of our geothermal projects under development and construction. These amendments (i) provided for a mechanism to share production tax credits with the relevant purchaser pursuant to a reduction in the price for electricity paid by the power purchaser under the relevant power purchase agreement, bringing additional power purchase agreements in line with the production tax credit sharing arrangements included in other power purchase agreements with these purchasers in Nevada, (ii) revised certain generation thresholds based on a more definitive understanding of the geothermal resource at the respective projects, and (iii) addressed certain delays in meeting contract milestones as a result of ordinary course project construction delays.

• In February 2008, we commenced commercial operation of the Galena 3 project at the Steamboat complex in Nevada.

• On January 8, 2008, we completed an unregistered sale of 693,750 shares of common stock to our parent, Ormat Industries Ltd., at a price of $48.02 per share, or approximately $33.3 million in the aggregate. The proceeds of that sale are being used for general corporate purposes, including construction of geothermal and recovered energy generation power plants and other investments, and the financing of possible acquisitions.

Trends and Uncertainties

The geothermal industry in the United States has historically experienced significant growth followed by a consolidation of owners and operators of geothermal power plants. During the 1990s, growth and development in the geothermal industry occurred primarily in foreign markets and only minimal growth and development occurred in the United States. Since 2001, there has been increased demand for energy generated from geothermal resources in the United States as production costs for electricity generated from geothermal resources have become more competitive relative to fossil fuel generation. This is partly due to increasing natural gas and oil prices and newly enacted legislative and regulatory incentives, such as state renewable portfolio standards. We see the increasing demand for energy generated from geothermal and other renewable resources in the United States and the further introduction of renewable portfolio standards as the most significant trends affecting our industry today and in the immediate future. Our operations and the trends that from time to time impact our operations are subject to market cycles.


Table of Contents

Although other trends, factors and uncertainties may impact our operations and financial condition, including many that we do not or cannot foresee, we believe that our results of operations and financial condition for the foreseeable future will be affected by the following trends, factors and uncertainties:

• The recent worldwide financial and credit crisis has reduced the availability of liquidity and credit to fund the continuation and expansion of industrial business operations worldwide. We have sufficient financial resources to fund our projected activities for 2009 and therefore, we did not change our current investment plans. If economic conditions worsen, the cost of obtaining financing for our project needs may increase significantly or such financing may not be available at all. See further discussion under "Exposure to Market Risks".

• Our primary focus continues to be the implementation of our organic growth through the construction of new projects and enhancements of several of our existing projects. We expect that this investment in organic growth will increase our total generating capacity, consolidated revenues and operating income attributable to our Electricity Segment year over year. We are also looking at acquisition opportunities that may arise as a result of the current financial crisis.

• Until the end of the third quarter we experienced increases in the cost of raw materials, labor and transportation costs required for our equipment manufacturing activities and equipment used in our power plants, as well as for sale to third parties. We also experienced an increase in drilling costs and a shortage in drilling equipment. We believe this was the result of the increased drilling activity in the marketplace in a high oil price environment. The recent decrease in the price of oil and other commodities may reduce such costs in the future.

• In the United States, we expect to continue to benefit from the increasing demand for renewable energy. Thirty-three states and the District of Columbia, including California, Nevada and Hawaii (where we have been most active in geothermal development and where all of our U.S. geothermal projects are located) have adopted renewable portfolio standards, renewable . . .

  Add ORA to Portfolio     Set Alert         Email to a Friend  
Get SEC Filings for Another Symbol: Symbol Lookup
Quotes & Info for ORA - All Recent SEC Filings
Sign Up for a Free Trial to the NEW EDGAR Online Pro
Detailed SEC, Financial, Ownership and Offering Data on over 12,000 U.S. Public Companies.
Actionable and easy-to-use with searching, alerting, downloading and more.
Request a Trial      Sign Up Now


Copyright © 2009 Yahoo! Inc. All rights reserved. Privacy Policy - Terms of Service
SEC Filing data and information provided by EDGAR Online, Inc. (1-800-416-6651). All information provided "as is" for informational purposes only, not intended for trading purposes or advice. Neither Yahoo! nor any of independent providers is liable for any informational errors, incompleteness, or delays, or for any actions taken in reliance on information contained herein. By accessing the Yahoo! site, you agree not to redistribute the information found therein.