Item 8.01 Other Events.
As of October 1, 2008, CenterPoint Energy, Inc.'s ("CenterPoint Energy")
electric transmission and distribution subsidiary, CenterPoint Energy Houston
Electric, LLC ("CenterPoint Houston") had restored service to approximately
99 percent of its customers following Hurricane Ike. Over 90 percent of
CenterPoint Houston's over 2 million customers initially were without electric
service after Hurricane Ike struck CenterPoint Houston's service territory on
September 13. Restoration work continues for a relatively small number of
customers, including customers needing customer-owned equipment repairs. Many of
the remaining outages involve customers who are unable to receive electric
service due to damaged electrical equipment or flooding. In addition to working
to restore service to remaining customers, CenterPoint Houston personnel are
inspecting work that has been done and making long term repairs where temporary
repairs were made during the initial stage of the restoration effort.
CenterPoint Houston is now phasing down its field workforce, which totaled as
many as 13,000 personnel from among its own employees and utilities and
contractors across the United States and Canada.
Some restoration and repair work is expected to continue during most of the
remainder of 2008, as customers rebuild homes and other facilities that were
severely damaged by the storm. Although CenterPoint Houston's facilities were
most severely damaged in heavily wooded areas, the most serious damage to
customer facilities tended to be concentrated in immediate coastal areas, such
as Galveston Island, which received damage both from Hurricane Ike's strong
winds and the associated tidal surge.
Total costs for the restoration effort still cannot be measured with
precision, but CenterPoint Houston now estimates that its costs will be in the
range of approximately $650 million to $750 million. Although the poles, towers,
wires, street lights and the pole mounted equipment that comprise CenterPoint
Houston's transmission and distribution system are not covered by property
insurance, office buildings and warehouses and their contents and substations
and their associated facilities are covered by insurance that provides for a
maximum deductible of $10 million. Current estimates are that total losses to
property covered by this insurance were approximately $25 million.
As reported previously, CenterPoint Houston is deferring the uninsured storm
restoration costs in the expectation of recovery through the regulatory process.
As a result, storm restoration costs will not affect CenterPoint Energy's or
CenterPoint Houston's reported net income for 2008. Assuming necessary enabling
legislation is enacted by the Texas Legislature in the session which begins in
January 2009, CenterPoint Houston expects to obtain recovery of its storm
restoration costs through the issuance of non-recourse securitization bonds
similar to the storm recovery bonds issued by another Texas utility following
Hurricane Rita. When those bonds are issued, CenterPoint Houston would recover
the amount of storm restoration costs approved by the Public Utility Commission
of Texas out of the bond proceeds, with the bonds being repaid over time through
a charge imposed on customers. Alternatively, if securitization is not
available, recovery of those costs would be sought through traditional
regulatory mechanisms. Under its 2006 rate case settlement, CenterPoint Houston
is entitled to seek an adjustment to rates in this situation, even though in
most instances its rates are frozen until 2010.
In addition to storm restoration costs, CenterPoint Houston has lost revenue
during the outage period, and will continue to lose some revenue that would
otherwise have been anticipated from those customers whose service will not be
restored for a longer period. As of October 1, CenterPoint Houston has restored
all but a minor portion of the load on its system, but the temporary outages
caused by the storm are expected to have a negative impact on CenterPoint
Energy's and CenterPoint Houston's earnings for the third quarter and for the
full year 2008. However, the exact amount of these impacts cannot be determined
at this time.
CenterPoint Energy and CenterPoint Houston continue to believe that they have
sufficient liquidity to finance storm restoration costs until ultimate recovery,
while at the same time carrying out their current business plans. If storm cost
recovery is delayed substantially, CenterPoint Energy and CenterPoint Houston
could be required to reduce funding on planned projects or to seek capital
resources not currently planned.
Capacity and usage of existing bank credit facilities of CenterPoint Energy
and CenterPoint Houston as of September 30, 2008 are shown in the table below
(in millions).
Size of Amount Utilized Amount Remaining
Company Facility at 9/30/2008 at 9/30/2008
CenterPoint Energy $ 1,200 $ 180 $ 1,020
CEHE $ 300 $ 174 $ 126
|
Also, CenterPoint Houston may obtain funds to finance costs associated with
its overall liquidity requirements or to reduce usage of bank credit facilities
through the issuance of general mortgage bonds or other capital markets
transactions.
In addition, CenterPoint Energy Resources Corp. ("CERC"), the natural gas
subsidiary of CenterPoint Energy, has its own $950 million bank credit facility,
of which $745 million was utilized at September 30, 2008. This facility is
available to fund CERC's business requirements, including the minimal impact to
CERC facilities from Hurricane Ike. The CERC facility would not be used to fund
CEHE's hurricane restoration costs.
The term of each credit facility extends to 2012. Amounts utilized are
subject to certain covenants, but based on unaudited financial information,
CenterPoint Energy and CenterPoint Houston believe they would have been entitled
to utilize substantially all of the capacity under their respective credit
facilities at September 30, 2008. However, Lehman Brothers Bank, FSB, whose
parent has filed for bankruptcy protection, has an approximately four percent
participation in each of the facilities but has not been funding its commitments
following the bankruptcy filing, effectively causing a minor reduction to the
total available capacity under the three facilities.